Ms Project Predessors w/two predessors
Project is built backwards from shipdate.
Task in question has two predessors. Need to have the system pick-up the earlier date rather than the later date. How? Task 20 Financial approval for purchase orders, with predessors of 30FS Place Purchase Order (8/28/09) and 40FS Place Purchase Order (10/01/09) minus two weeks. Task 20 calualates 9/17/09 (coming from task 40) instead of task 30fs-2wks, 8/14/09. Donab |
#2
Posted to microsoft.public.excel.newusers
|
|||
|
|||
Ms Project Predessors w/two predessors
Maybe try a project newsgroup rather than Excel?
-- __________________________________ HTH Bob "Donab" wrote in message ... Project is built backwards from shipdate. Task in question has two predessors. Need to have the system pick-up the earlier date rather than the later date. How? Task 20 Financial approval for purchase orders, with predessors of 30FS Place Purchase Order (8/28/09) and 40FS Place Purchase Order (10/01/09) minus two weeks. Task 20 calualates 9/17/09 (coming from task 40) instead of task 30fs-2wks, 8/14/09. Donab |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Excell error "Can't find Project or Library" Project VBAProject | Excel Worksheet Functions | |||
How to convert MS Project to MS Excel. I don't have MS Project. | Excel Discussion (Misc queries) | |||
Help with a project | Excel Discussion (Misc queries) | |||
Need a project. | New Users to Excel | |||
I pay $ for this project | Charts and Charting in Excel |