I want to find the no of days b/w two days it should consider saturday as
half day holiday and sunday as fully day holiday . and any holidays in that
week

I need ans at c1= 11 . In between 1 and 15, date 14 is holiday.

A B C D E
F G

1 1-Jan-10 15-Jan-10


One more thing


In a1 = Project Start Month , b1= Jan-10
In a2 = Project Duration , b2= 10 ( which may change depend upon the project)


I need a formula so that from it shows
a5=Jan-10
a6= Feb-10
a7= Mar-10 ...... so on depend upon the value in B2 cell
  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 2,203
Default No of Days between two dates and offset formula

Not sure I can help with needed formula in C1. I think I could do it with a
User Defined Function (VBA code), but someone may come along with an answer.

Meanwhile, for the formulas needed starting at A5, try this:
=IF(ROW()-ROW(A$5)+1<=B$2,DATE(YEAR(B$1),MONTH(B$2)+ROW()-ROW(A$5),DAY(B$1)),"")
Fill down the sheet as far as you care to go. It will show a blank cell
starting when you get beyond the # of months duration in B2. The 'secret' is
in the
ROW() - ROW(A$5) parts. ROW(A$5) is always going to evaluate to 5. Since
we are starting at row 5, current row - 5=0, when the formula moves to row 6,
then (currentrow=6)-5 = 1 so we get the next month.
You could write it as
=IF(ROW()-5+1<=B$2,DATE(YEAR(B$1),MONTH(B$2)+ROW()-5,DAY(B$1)),"")
But I think using the ROW(A$5) gives someone reading the formulas months
from now a little clue as to what is going on - they should see that row 5 is
the first row with the formula in it.





"vmohan1978" wrote:

I want to find the no of days b/w two days it should consider saturday as
half day holiday and sunday as fully day holiday . and any holidays in that
week

I need ans at c1= 11 . In between 1 and 15, date 14 is holiday.

A B C D E
F G

1 1-Jan-10 15-Jan-10


One more thing


In a1 = Project Start Month , b1= Jan-10
In a2 = Project Duration , b2= 10 ( which may change depend upon the project)


I need a formula so that from it shows
a5=Jan-10
a6= Feb-10
a7= Mar-10 ...... so on depend upon the value in B2 cell

  #3   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 2,203
Default No of Days between two dates and offset formula

For the formula needed in C1, you could look at the NETWORKDAYS() function.
This is part of an Add-In called the Analysis ToolPak. You'll need to
'install' that add-in if you haven't already to use NETWORKDAYS(). Search
Excel Help for NETWORKDAYS() for all the details.

Basically NETWORKDAYS() gives you a total of the days between 2 days but
automatically considers both Saturday and Sunday as non-work days. So you
would have an 'error' of 0.5 days per week.
With A1 = 1-Jan-2010 and B1 = 15-JAN-2010, then
=NETWORKDAYS(A1,B1) gives you a result of 11, as you asked for. But I think
that may be a 'special' case because of Jan 01.
If you enter dates of 1/4/2010 and 1/18/2010, then the result is 11, and I'm
thinking that you really expect to see 12 in this case: the formula has
subtracted 2 whole days for the two Saturdays, but you only want to subtract
2x0.5 or 1 day per 2 Saturdays.


"vmohan1978" wrote:

I want to find the no of days b/w two days it should consider saturday as
half day holiday and sunday as fully day holiday . and any holidays in that
week

I need ans at c1= 11 . In between 1 and 15, date 14 is holiday.

A B C D E
F G

1 1-Jan-10 15-Jan-10


One more thing


In a1 = Project Start Month , b1= Jan-10
In a2 = Project Duration , b2= 10 ( which may change depend upon the project)


I need a formula so that from it shows
a5=Jan-10
a6= Feb-10
a7= Mar-10 ...... so on depend upon the value in B2 cell

  #4   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 38
Default No of Days between two dates and offset formula

Dear JLatham,
Thank you very much it worked Perfectly. It saved my time lot.


"JLatham" wrote:

Not sure I can help with needed formula in C1. I think I could do it with a
User Defined Function (VBA code), but someone may come along with an answer.

Meanwhile, for the formulas needed starting at A5, try this:
=IF(ROW()-ROW(A$5)+1<=B$2,DATE(YEAR(B$1),MONTH(B$2)+ROW()-ROW(A$5),DAY(B$1)),"")
Fill down the sheet as far as you care to go. It will show a blank cell
starting when you get beyond the # of months duration in B2. The 'secret' is
in the
ROW() - ROW(A$5) parts. ROW(A$5) is always going to evaluate to 5. Since
we are starting at row 5, current row - 5=0, when the formula moves to row 6,
then (currentrow=6)-5 = 1 so we get the next month.
You could write it as
=IF(ROW()-5+1<=B$2,DATE(YEAR(B$1),MONTH(B$2)+ROW()-5,DAY(B$1)),"")
But I think using the ROW(A$5) gives someone reading the formulas months
from now a little clue as to what is going on - they should see that row 5 is
the first row with the formula in it.





"vmohan1978" wrote:

I want to find the no of days b/w two days it should consider saturday as
half day holiday and sunday as fully day holiday . and any holidays in that
week

I need ans at c1= 11 . In between 1 and 15, date 14 is holiday.

A B C D E
F G

1 1-Jan-10 15-Jan-10


One more thing


In a1 = Project Start Month , b1= Jan-10
In a2 = Project Duration , b2= 10 ( which may change depend upon the project)


I need a formula so that from it shows
a5=Jan-10
a6= Feb-10
a7= Mar-10 ...... so on depend upon the value in B2 cell

  #5   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 38
Default No of Days between two dates and offset formula

Hi JLatham,
Thank you very much.

I tried the networkdays() formula but it consider both sat and sun as
holiday . but i require sat as half day.



"JLatham" wrote:

For the formula needed in C1, you could look at the NETWORKDAYS() function.
This is part of an Add-In called the Analysis ToolPak. You'll need to
'install' that add-in if you haven't already to use NETWORKDAYS(). Search
Excel Help for NETWORKDAYS() for all the details.

Basically NETWORKDAYS() gives you a total of the days between 2 days but
automatically considers both Saturday and Sunday as non-work days. So you
would have an 'error' of 0.5 days per week.
With A1 = 1-Jan-2010 and B1 = 15-JAN-2010, then
=NETWORKDAYS(A1,B1) gives you a result of 11, as you asked for. But I think
that may be a 'special' case because of Jan 01.
If you enter dates of 1/4/2010 and 1/18/2010, then the result is 11, and I'm
thinking that you really expect to see 12 in this case: the formula has
subtracted 2 whole days for the two Saturdays, but you only want to subtract
2x0.5 or 1 day per 2 Saturdays.


"vmohan1978" wrote:

I want to find the no of days b/w two days it should consider saturday as
half day holiday and sunday as fully day holiday . and any holidays in that
week

I need ans at c1= 11 . In between 1 and 15, date 14 is holiday.

A B C D E
F G

1 1-Jan-10 15-Jan-10


One more thing


In a1 = Project Start Month , b1= Jan-10
In a2 = Project Duration , b2= 10 ( which may change depend upon the project)


I need a formula so that from it shows
a5=Jan-10
a6= Feb-10
a7= Mar-10 ...... so on depend upon the value in B2 cell

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
formula for # of days between two dates-Excel 2000 kelley Excel Discussion (Misc queries) 1 June 29th 07 06:52 PM
How do I use the IF formula to flag dates 21 days prior to deadlin Wanderer Excel Worksheet Functions 1 September 26th 06 01:29 PM
Need formula to calculate days between dates or back date KVN Excel Discussion (Misc queries) 3 May 3rd 06 10:08 PM
Formula to calculate number of days between Dates themax16 Excel Worksheet Functions 2 October 21st 05 01:38 PM
formula to find and flag dates older than 30 days Will G. Excel Worksheet Functions 1 June 18th 05 12:13 AM


All times are GMT +1. The time now is 02:06 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"