Home |
Search |
Today's Posts |
#1
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Non working time
I have a spreadsheet to plan production over a 24 hour period. This
works fine but we are now moving to a 2 shift pattern so there will be 4 hours non productive time every day. The current formula uses simple arithmetic adding a task duration onto the finish time for the last task. I now need to factor in the extra time should a task span the period of non production. Thanks Martin B |
#2
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Non working time
Work through a couple of examples.
-- __________________________________ HTH Bob " wrote in message ... I have a spreadsheet to plan production over a 24 hour period. This works fine but we are now moving to a 2 shift pattern so there will be 4 hours non productive time every day. The current formula uses simple arithmetic adding a task duration onto the finish time for the last task. I now need to factor in the extra time should a task span the period of non production. Thanks Martin B |
#3
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Non working time
Hi,
Show us a sample of the data and the results you expect. Thanks, Shane Devenshire " wrote: I have a spreadsheet to plan production over a 24 hour period. This works fine but we are now moving to a 2 shift pattern so there will be 4 hours non productive time every day. The current formula uses simple arithmetic adding a task duration onto the finish time for the last task. I now need to factor in the extra time should a task span the period of non production. Thanks Martin B |
#4
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Non working time
On Dec 2, 4:46*am, Shane Devenshire
wrote: Hi, Show us a sample of the data and the results you expect. Thanks, Shane Devenshire " wrote: I have a spreadsheet to plan production over a 24 hour period. This works fine but we are now moving to a 2 shift pattern so there will be 4 hours non productive time every day. The current formula uses simple arithmetic adding a task duration onto the finish time for the last task. I now need to factor in the extra time should a task span the period of non production. Thanks Martin B- Hide quoted text - - Show quoted text - Sorry, should have been more specific. Lets say task duration in A1 = 10hrs Start time in B1 = 09:00 Predicted completion time in C1 should be 23:00 as 4 hours non productive time in the afternoon 16:00 to 20:00. If the task duration was 6 hours completion time would be 15:00 as it could be completed in the morning shift. I only need to consider the non productive time in the afternoon if the job spans from the morning shift into the night shift. Hope that's a bit clearer Martin |
#5
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Non working time
It depends when the second shift kicks in, but assuming 5PM
=B1+A1/24+IF(B1+A1/24--"17:00","4:00",0) -- __________________________________ HTH Bob " wrote in message ... On Dec 2, 4:46 am, Shane Devenshire wrote: Hi, Show us a sample of the data and the results you expect. Thanks, Shane Devenshire " wrote: I have a spreadsheet to plan production over a 24 hour period. This works fine but we are now moving to a 2 shift pattern so there will be 4 hours non productive time every day. The current formula uses simple arithmetic adding a task duration onto the finish time for the last task. I now need to factor in the extra time should a task span the period of non production. Thanks Martin B- Hide quoted text - - Show quoted text - Sorry, should have been more specific. Lets say task duration in A1 = 10hrs Start time in B1 = 09:00 Predicted completion time in C1 should be 23:00 as 4 hours non productive time in the afternoon 16:00 to 20:00. If the task duration was 6 hours completion time would be 15:00 as it could be completed in the morning shift. I only need to consider the non productive time in the afternoon if the job spans from the morning shift into the night shift. Hope that's a bit clearer Martin |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
working out a sum in time? | Excel Discussion (Misc queries) | |||
VLOOKUP not working all the time... | Excel Discussion (Misc queries) | |||
Working with Time | Excel Worksheet Functions | |||
formula help working with time | Excel Discussion (Misc queries) | |||
Working with If statements and time | Excel Worksheet Functions |