Default Problem with working days

Give the following function a try...

Function AddWorkDays(StartDate As Date, WorkDays As Long) As Date
If WorkDays < 0 Then Exit Function
AddWorkDays = DateAdd("d", 7 * (WorkDays \ 5) + (WorkDays Mod 5) - _
2 * ((WorkDays Mod 5) Abs(5 + - _
Weekday(StartDate, vbMonday))) + _
Weekday(StartDate, vbSaturday) * _
(Weekday(StartDate, vbSaturday) < 3), StartDate)
End Function

As written, this function will only *add* workdays to the StartDate. If the
WorkDays value is less than 0, then "day zero" (12/30/1899) is returned and
can be used for error checking purposes.

--
Rick (MVP - Excel)


"JillC" wrote in message
...
How can I ensure that if I add a number of days to a date (which is a
working
date) the result will also be a work date
--
Thanks, Jill


 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculate working days but change working week SamB Excel Discussion (Misc queries) 1 September 1st 08 09:17 PM
Making weekend days working days - the system cuts the working tim Fluffy Excel Discussion (Misc queries) 1 May 30th 08 10:02 PM
How to calculation no. of days (only working days) between two dat Vivian Chan Excel Discussion (Misc queries) 1 July 26th 07 09:16 AM
Non working days The Rook[_2_] Excel Discussion (Misc queries) 4 March 31st 07 09:00 PM
Working Days Norman Harker Excel Programming 0 January 20th 04 03:12 PM


All times are GMT +1. The time now is 03:43 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"