#1
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Have tried all of the formulas relating to time date diff but cannot get the
weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
#2
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Why should it be 8. When does the day start and end?
-- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Have tried all of the formulas relating to time date diff but cannot get the weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
#3
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
As I am ultimatly trying to get a cost for labour and the day starts @ 07:30
and finishes @ 16:00 JMB "Bob Phillips" wrote: Why should it be 8. When does the day start and end? -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Have tried all of the formulas relating to time date diff but cannot get the weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
#4
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
I make that 8.5. So where does the break kick in? It al matters for the
solution. -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... As I am ultimatly trying to get a cost for labour and the day starts @ 07:30 and finishes @ 16:00 JMB "Bob Phillips" wrote: Why should it be 8. When does the day start and end? -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Have tried all of the formulas relating to time date diff but cannot get the weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
#5
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Bob,
OK, yes it's 8.5 Hrs...The break starts @ 16:00 on a Friday afternoon and ends on Mondays @ 07:30. The idea is that we have supplimentry labour on site and need to calculate the number of hours X payrate to get a total cost for a given time period. JMB "Bob Phillips" wrote: I make that 8.5. So where does the break kick in? It al matters for the solution. -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... As I am ultimatly trying to get a cost for labour and the day starts @ 07:30 and finishes @ 16:00 JMB "Bob Phillips" wrote: Why should it be 8. When does the day start and end? -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Have tried all of the formulas relating to time date diff but cannot get the weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
#6
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Try this
=(NETWORKDAYS(A1,A2)-(WEEKDAY(A1,2)<6)-(WEEKDAY(A2,2)<6))*8.5+ (IF(WEEKDAY(A1,2)<6,MIN(MAX((TIME(16,0,0)-MOD(A1,1))*24,0),8.5),0))+ (IF(WEEKDAY(A2,2)<6,MIN(MAX((MOD(A2,1)-TIME(7,30,0))*24,0),8.5),0)) -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Bob, OK, yes it's 8.5 Hrs...The break starts @ 16:00 on a Friday afternoon and ends on Mondays @ 07:30. The idea is that we have supplimentry labour on site and need to calculate the number of hours X payrate to get a total cost for a given time period. JMB "Bob Phillips" wrote: I make that 8.5. So where does the break kick in? It al matters for the solution. -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... As I am ultimatly trying to get a cost for labour and the day starts @ 07:30 and finishes @ 16:00 JMB "Bob Phillips" wrote: Why should it be 8. When does the day start and end? -- --- HTH Bob (there's no email, no snail mail, but somewhere should be gmail in my addy) "JMB" wrote in message ... Have tried all of the formulas relating to time date diff but cannot get the weekend hours out of the equation eg C3 = 14-Mar-2008 07:30 C4 = 17-Mar-2008 07:30 C5 = should equal 8 How or what determains the hrs which are output. I have tried the formular using netwokdays & workdays. Thanks JMB. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
date and time difference | Excel Worksheet Functions | |||
Difference in date and time | Excel Discussion (Misc queries) | |||
Date and time difference | Excel Worksheet Functions | |||
Calculating Difference Between Start Date & Time And End Date & Ti | Excel Discussion (Misc queries) | |||
Difference of date & time in minutes | Excel Worksheet Functions |