how to calculate based on dates?
I want to calculate whether total payments are ahead or behind of schedule.
Column A is for Dates. Column L is the difference between J$6 and J(whatever selected row). The number in Column L gets larger, row by row. I want to have a Column M that calculates how much the figures in column L are ahead or behind plan. The plan is for column L to increase at 53 per day. The entries and the dates entered in Column A are not daily (or in any regular periodic sequence), but they are chronological of course. Working with the dates is confusing me -- can anyone help?! Thanks, Jack |
#2
Posted to microsoft.public.excel.misc
|
|||
|
|||
how to calculate based on dates?
Perhaps this table (if it shows up right) will make things clearer:
A J K L M Date Total credit debt Amt of credit debt reduced Cummula-tive credit reduction Credit reduction ahead or behind (-) 20-Jul 15,629.33 na na na 6-Sep 13,115.73 2,513.60 2,513.60 20-Oct 12,834.65 281.08 3,244.05 13-Nov 12,104.20 730.45 3,525.13 "Jack B" wrote in message ... I want to calculate whether total payments are ahead or behind of schedule. Column A is for Dates. Column L is the difference between J$6 and J(whatever selected row). The number in Column L gets larger, row by row. I want to have a Column M that calculates how much the figures in column L are ahead or behind plan. The plan is for column L to increase at 53 per day. The entries and the dates entered in Column A are not daily (or in any regular periodic sequence), but they are chronological of course. Working with the dates is confusing me -- can anyone help?! Thanks, Jack |
#3
Posted to microsoft.public.excel.misc
|
|||
|
|||
how to calculate based on dates?
Well, that post didn't work out -- see the table at
http://home.earthlink.net/~holysmoke...alculation.gif Jack |
#4
Posted to microsoft.public.excel.misc
|
|||
|
|||
how to calculate based on dates?
I guess I thought it was harder than it really is.
This seems to work [Column L is the difference between J$5 and J(whatever selected row)]: =IF(ISNUMBER(L6),($A$5-A6)*53+L6,"") Jack --------------------------------------- "Jack B" wrote in message ... I want to calculate whether total payments are ahead or behind of schedule. Column A is for Dates. Column L is the difference between J$6 and J(whatever selected row). The number in Column L gets larger, row by row. I want to have a Column M that calculates how much the figures in column L are ahead or behind plan. The plan is for column L to increase at 53 per day. The entries and the dates entered in Column A are not daily (or in any regular periodic sequence), but they are chronological of course. Working with the dates is confusing me -- can anyone help?! Thanks, Jack |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
How do I calculate exact difference between two dates in y,m,d. | Excel Worksheet Functions | |||
Count data based on past dates | Excel Worksheet Functions | |||
Need formula to calculate days between dates or back date | Excel Discussion (Misc queries) | |||
Determining Date X based on Other dates | Excel Worksheet Functions | |||
Rank items, select one start date, have remaining dates follow based on rank | Excel Discussion (Misc queries) |