Hi,

I wonder if anyone can help. I have a table with three columns.

€’ Column A shows the start date of a task
€’ Column C shows the tasks duration
€’ Column B adds the number of days in column C to the start date in column A
to arrive at the tasks end date.

I want column B, instead of adding €˜x number of days to the start date to
add €˜x number of working days. Can anyone tell me how to do this?

Ive been playing around with the NETWORKDAYS function, but cant find a way
to do just what I want.

Thanks

Karl

  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 202
Default Adding network days

=TEXT(WORKDAY(A1,C1),"dd/mm/yyyy")

"Karl" wrote:


Hi,

I wonder if anyone can help. I have a table with three columns.

€’ Column A shows the start date of a task
€’ Column C shows the tasks duration
€’ Column B adds the number of days in column C to the start date in column A
to arrive at the tasks end date.

I want column B, instead of adding €˜x number of days to the start date to
add €˜x number of working days. Can anyone tell me how to do this?

Ive been playing around with the NETWORKDAYS function, but cant find a way
to do just what I want.

Thanks

Karl

  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 8,651
Default Adding network days

Did the OP ask for text? Why not just =WORKDAY(A1,C1) [formatted to suit
the OP's preferences] ?
That way, the OP will end up with a result on which he can do further
calculations if he wishes to do so.
--
David Biddulph

"Dennis" wrote in message
...
=TEXT(WORKDAY(A1,C1),"dd/mm/yyyy")

"Karl" wrote:


Hi,

I wonder if anyone can help. I have a table with three columns.

. Column A shows the start date of a task
. Column C shows the task's duration
. Column B adds the number of days in column C to the start date in
column A
to arrive at the task's end date.

I want column B, instead of adding 'x' number of days to the start date
to
add 'x' number of working days. Can anyone tell me how to do this?

I've been playing around with the NETWORKDAYS function, but can't find a
way
to do just what I want.

Thanks

Karl



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Network days rounding off hours Thomas T Excel Discussion (Misc queries) 7 March 31st 08 01:53 PM
Network days - Returns error sometimes. Matts Excel Discussion (Misc queries) 1 November 19th 07 03:38 PM
IF statement and Network days Kim Excel Discussion (Misc queries) 2 February 15th 07 11:54 PM
Network Days dinadvani via OfficeKB.com Excel Discussion (Misc queries) 3 July 21st 06 11:05 AM
Network days question Annette Excel Worksheet Functions 2 June 29th 06 04:18 PM


All times are GMT +1. The time now is 02:47 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"