  #1   Report Post  
Posted to microsoft.public.excel.setup
external usenet poster
 
Posts: 1
Default How do I set an automatic working days counter

I need to set an automatic working days (Mon to Fri) counter so the date can
be updated automatically. I want to use this automatic counter to track
projects, to check how many days does the project has or left.
  #2   Report Post  
Posted to microsoft.public.excel.setup
external usenet poster
 
Posts: 3,101
Default How do I set an automatic working days counter

With a start date for your project in A2

=NETWORKDAYS(A2,NOW())

will return how many weekdays your project has been running for.

With the planned end date in B2

=NETWORKDAYS(NOW(),B2)

Will return the number of days remaining. Note that this last formula will
go negative if your project overruns



"Selekeng" wrote:

I need to set an automatic working days (Mon to Fri) counter so the date can
be updated automatically. I want to use this automatic counter to track
projects, to check how many days does the project has or left.

  #3   Report Post  
Posted to microsoft.public.excel.setup
external usenet poster
 
Posts: 119
Default How do I set an automatic working days counter

You can also expand that to not count bank holidays etc by including a list
of dates which you're not working for - Forumlas as below, but add a comma
and then a reference to the range including the dates, e.g:

A5 25/12/2007
A6 26/12/2007
A7 01/01/2008

=NETWORKDAYS(A2,NOW(),A5:A7)

Hope this helps.

Tom.

"Mike" wrote:

With a start date for your project in A2

=NETWORKDAYS(A2,NOW())

will return how many weekdays your project has been running for.

With the planned end date in B2

=NETWORKDAYS(NOW(),B2)

Will return the number of days remaining. Note that this last formula will
go negative if your project overruns



"Selekeng" wrote:

I need to set an automatic working days (Mon to Fri) counter so the date can
be updated automatically. I want to use this automatic counter to track
projects, to check how many days does the project has or left.

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Working days Andrew Mackenzie Excel Discussion (Misc queries) 8 January 3rd 07 02:39 PM
Add on 8 working days to a date Shirley Munro Excel Worksheet Functions 2 March 9th 06 02:57 PM
Working Days Mike Hebblewhite Excel Discussion (Misc queries) 1 January 30th 06 11:49 AM
Working Days Mike Hebblewhite Excel Discussion (Misc queries) 0 January 30th 06 11:00 AM
How to Add 5 working days Trying2Learn Excel Discussion (Misc queries) 1 June 20th 05 12:52 PM


All times are GMT +1. The time now is 10:01 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"