How do I set an automatic working days counter
I need to set an automatic working days (Mon to Fri) counter so the date can
be updated automatically. I want to use this automatic counter to track projects, to check how many days does the project has or left. |
How do I set an automatic working days counter
With a start date for your project in A2
=NETWORKDAYS(A2,NOW()) will return how many weekdays your project has been running for. With the planned end date in B2 =NETWORKDAYS(NOW(),B2) Will return the number of days remaining. Note that this last formula will go negative if your project overruns "Selekeng" wrote: I need to set an automatic working days (Mon to Fri) counter so the date can be updated automatically. I want to use this automatic counter to track projects, to check how many days does the project has or left. |
How do I set an automatic working days counter
You can also expand that to not count bank holidays etc by including a list
of dates which you're not working for - Forumlas as below, but add a comma and then a reference to the range including the dates, e.g: A5 25/12/2007 A6 26/12/2007 A7 01/01/2008 =NETWORKDAYS(A2,NOW(),A5:A7) Hope this helps. Tom. "Mike" wrote: With a start date for your project in A2 =NETWORKDAYS(A2,NOW()) will return how many weekdays your project has been running for. With the planned end date in B2 =NETWORKDAYS(NOW(),B2) Will return the number of days remaining. Note that this last formula will go negative if your project overruns "Selekeng" wrote: I need to set an automatic working days (Mon to Fri) counter so the date can be updated automatically. I want to use this automatic counter to track projects, to check how many days does the project has or left. |