Default WORKDAY Function

I've read, read, and read about the WORKDAY function (Excel Help and online)
and cannot find a solution as to why my formula is giving me #NUM!. I read
the reasons why, but cannot find any errors. All columns with dates are
formated to 'date'. Analysis Toolpak is checked in Tools/Add-ins. The
formula in I3 is this: =WORKDAY(J3,1,NWD)
€¢ J3 is the date 16-Feb-10, formatted as date (format cells, etc.)
€¢ J3's date comes from a VLOOKUP function, from a column that is formatted
as a date
€¢ NWD (meaning "non-workdays") is a named range in another worksheet of the
same workbook, and is formatted as a date (format cells, etc.).
€¢ NWD was inserted into the formula by Insert/Name/Paste
€¢ With this formula in I3 it should give 17-Feb-10. Very simple, this one.
But it gives me #NUM!.
Can anyone shed some light on this? It's getting very frustrating! I would
be so very, very grateful if you could. Thank you. Connie

  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 2,722
Default WORKDAY Function

Agreed, very confusing. From my tests, is appears WORKDAY is able to handle a
start date formatted as text, so that can't be the problem. You clearly have
an legitimate number in the days arguement...

The only thing I was able to do that created a #NUM error in your scenario
was to have a negative number in the NWD range. This is a slim chance, but
possibly?

Further debugging:
Does
=WORKDAY(J3,1)
work?

Instead of using the named range, manually input an address, starting with a
smaller size, and gradually increasing until the error is generated.

Sorry I wasn't able to find a easy solution.
--
Best Regards,

Luke M
*Remember to click "yes" if this post helped you!*


"Connie Martin" wrote:

I've read, read, and read about the WORKDAY function (Excel Help and online)
and cannot find a solution as to why my formula is giving me #NUM!. I read
the reasons why, but cannot find any errors. All columns with dates are
formated to 'date'. Analysis Toolpak is checked in Tools/Add-ins. The
formula in I3 is this: =WORKDAY(J3,1,NWD)
€¢ J3 is the date 16-Feb-10, formatted as date (format cells, etc.)
€¢ J3's date comes from a VLOOKUP function, from a column that is formatted
as a date
€¢ NWD (meaning "non-workdays") is a named range in another worksheet of the
same workbook, and is formatted as a date (format cells, etc.).
€¢ NWD was inserted into the formula by Insert/Name/Paste
€¢ With this formula in I3 it should give 17-Feb-10. Very simple, this one.
But it gives me #NUM!.
Can anyone shed some light on this? It's getting very frustrating! I would
be so very, very grateful if you could. Thank you. Connie

  #3   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 251
Default WORKDAY Function

Luke, thank you so much for replying. Your debug test worked. So the
problem was in the named range. I did the next thing you said, and put in
the range A1:A10 in the formula instead of NWD, the named range, and formula
worked! So, I looked at the named range, as it had to be the problem. When
I named the range, I selected the entire column instead of just the cells
with dates. So, I deleted the named range, selected just the dates A1:A10
and renamed it NWD, and the formula works! Marvelous! Oh! I'm so happy!
Now I can go places!! Thank you a million times! Connie

"Luke M" wrote:

Agreed, very confusing. From my tests, is appears WORKDAY is able to handle a
start date formatted as text, so that can't be the problem. You clearly have
an legitimate number in the days arguement...

The only thing I was able to do that created a #NUM error in your scenario
was to have a negative number in the NWD range. This is a slim chance, but
possibly?

Further debugging:
Does
=WORKDAY(J3,1)
work?

Instead of using the named range, manually input an address, starting with a
smaller size, and gradually increasing until the error is generated.

Sorry I wasn't able to find a easy solution.
--
Best Regards,

Luke M
*Remember to click "yes" if this post helped you!*


"Connie Martin" wrote:

I've read, read, and read about the WORKDAY function (Excel Help and online)
and cannot find a solution as to why my formula is giving me #NUM!. I read
the reasons why, but cannot find any errors. All columns with dates are
formated to 'date'. Analysis Toolpak is checked in Tools/Add-ins. The
formula in I3 is this: =WORKDAY(J3,1,NWD)
€¢ J3 is the date 16-Feb-10, formatted as date (format cells, etc.)
€¢ J3's date comes from a VLOOKUP function, from a column that is formatted
as a date
€¢ NWD (meaning "non-workdays") is a named range in another worksheet of the
same workbook, and is formatted as a date (format cells, etc.).
€¢ NWD was inserted into the formula by Insert/Name/Paste
€¢ With this formula in I3 it should give 17-Feb-10. Very simple, this one.
But it gives me #NUM!.
Can anyone shed some light on this? It's getting very frustrating! I would
be so very, very grateful if you could. Thank you. Connie

  #4   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 2,722
Default WORKDAY Function

Hurrah, glad it helped.

Furhter study:
I thought at first the problem with having the whole column called out was
all the blank cells, but it's not. It simply can't handle calling out the
entire column. Ironically, if you try this:
=WORKDAY(A1,1,B1:B65535)
you're ok, but if you try to include that last cell:
=WORKDAY(A1,1,B1:B65536)
XL will "help" you out can change the final address to simply B:B, and then
crash the formula!
--
Best Regards,

Luke M
*Remember to click "yes" if this post helped you!*


"Connie Martin" wrote:

Luke, thank you so much for replying. Your debug test worked. So the
problem was in the named range. I did the next thing you said, and put in
the range A1:A10 in the formula instead of NWD, the named range, and formula
worked! So, I looked at the named range, as it had to be the problem. When
I named the range, I selected the entire column instead of just the cells
with dates. So, I deleted the named range, selected just the dates A1:A10
and renamed it NWD, and the formula works! Marvelous! Oh! I'm so happy!
Now I can go places!! Thank you a million times! Connie

"Luke M" wrote:

Agreed, very confusing. From my tests, is appears WORKDAY is able to handle a
start date formatted as text, so that can't be the problem. You clearly have
an legitimate number in the days arguement...

The only thing I was able to do that created a #NUM error in your scenario
was to have a negative number in the NWD range. This is a slim chance, but
possibly?

Further debugging:
Does
=WORKDAY(J3,1)
work?

Instead of using the named range, manually input an address, starting with a
smaller size, and gradually increasing until the error is generated.

Sorry I wasn't able to find a easy solution.
--
Best Regards,

Luke M
*Remember to click "yes" if this post helped you!*


"Connie Martin" wrote:

I've read, read, and read about the WORKDAY function (Excel Help and online)
and cannot find a solution as to why my formula is giving me #NUM!. I read
the reasons why, but cannot find any errors. All columns with dates are
formated to 'date'. Analysis Toolpak is checked in Tools/Add-ins. The
formula in I3 is this: =WORKDAY(J3,1,NWD)
€¢ J3 is the date 16-Feb-10, formatted as date (format cells, etc.)
€¢ J3's date comes from a VLOOKUP function, from a column that is formatted
as a date
€¢ NWD (meaning "non-workdays") is a named range in another worksheet of the
same workbook, and is formatted as a date (format cells, etc.).
€¢ NWD was inserted into the formula by Insert/Name/Paste
€¢ With this formula in I3 it should give 17-Feb-10. Very simple, this one.
But it gives me #NUM!.
Can anyone shed some light on this? It's getting very frustrating! I would
be so very, very grateful if you could. Thank you. Connie

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Using WORKDAY function Frik Excel Discussion (Misc queries) 4 June 19th 07 12:27 PM
WORKDAY function jpac Excel Worksheet Functions 1 December 22nd 06 09:50 PM
Workday function RUSH2CROCHET Excel Discussion (Misc queries) 4 May 17th 06 07:34 PM
Workday function 4110 Excel Worksheet Functions 0 January 19th 06 03:02 PM
How do I get the WORKDAY function? jorfo Excel Discussion (Misc queries) 1 December 4th 04 11:01 PM


All times are GMT +1. The time now is 12:11 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"