Home |
Search |
Today's Posts |
#1
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Hi,
Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#2
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Set up a list of holiday dates to be excluded. Assume this list is in the
range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#3
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
NM wrote:
Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. Look at the NETWORKDAYS() function. |
#4
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Glenn wrote:
NM wrote: Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. Look at the NETWORKDAYS() function. As Biff pointed out, WORKDAYS() is the correct function for your task. |
#5
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Try this
=WORKDAY(A1,B1,Holidays) Holidays is a named rtange that contains any holidaya dates. If you get a NAME# error then Tools|addins and load the analysis toolpak. Mike "NM" wrote: Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#6
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Forgot to mention:
WORKDAY returns the date serial number so you'll have to format the formula cells as Date. -- Biff Microsoft Excel MVP "T. Valko" wrote in message ... Set up a list of holiday dates to be excluded. Assume this list is in the range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#7
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
On Tue, 9 Dec 2008 11:08:12 -0800, NM wrote:
Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. Check HELP for the WORKDAY function. If you are using a version of Excel prior to 2007, read HELP carefully for the "fix" in case you get a #NAME! error when trying the function. =WORKDAY(A1,B1,[holidays]) Holidays is an optional argument which is an array of holiday dates. So you might have them listed in some range somewhere. --ron |
#8
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Use the WORKDAY function. Look it up in Excel help.
-- David Biddulph "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#9
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
What is the easiest way to set up a list of weekends and holidays?
"T. Valko" wrote: Set up a list of holiday dates to be excluded. Assume this list is in the range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#10
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
You don't need to list the weekend dates, the WORKDAY function knows to
exclude those but you have to list any holiday dates that you want to exclude from the calculation. You simply enter those dates in a range of cells: J1: 1/1/2009 J2: 1/2/2009 J3: 2/21/2009 J4: 5/31/2009 J5: 7/4/2009 etc etc etc -- Biff Microsoft Excel MVP "NM" wrote in message ... What is the easiest way to set up a list of weekends and holidays? "T. Valko" wrote: Set up a list of holiday dates to be excluded. Assume this list is in the range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#11
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Hello,
One example for US bank holidays: http://www.sulprobil.com/html/holiday_table.html Regards, Bernd |
#12
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
I am still getting NAME # error!
"Mike H" wrote: Try this =WORKDAY(A1,B1,Holidays) Holidays is a named rtange that contains any holidaya dates. If you get a NAME# error then Tools|addins and load the analysis toolpak. Mike "NM" wrote: Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#13
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
How can I use the 'Workday' function with 'If' statement.
eg. If column A is empty then it should pick up the date from column c, if column C is empty is should pick up the date which is in column D and the same for column E? Thanks for you help. "T. Valko" wrote: You don't need to list the weekend dates, the WORKDAY function knows to exclude those but you have to list any holiday dates that you want to exclude from the calculation. You simply enter those dates in a range of cells: J1: 1/1/2009 J2: 1/2/2009 J3: 2/21/2009 J4: 5/31/2009 J5: 7/4/2009 etc etc etc -- Biff Microsoft Excel MVP "NM" wrote in message ... What is the easiest way to set up a list of weekends and holidays? "T. Valko" wrote: Set up a list of holiday dates to be excluded. Assume this list is in the range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
#14
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
Sum working days
Try this:
=WORKDAY(IF(A1="",IF(C1="",IF(D1="",E1,D1),C1),A1) ,B1,J1:J10) -- Biff Microsoft Excel MVP "NM" wrote in message ... How can I use the 'Workday' function with 'If' statement. eg. If column A is empty then it should pick up the date from column c, if column C is empty is should pick up the date which is in column D and the same for column E? Thanks for you help. "T. Valko" wrote: You don't need to list the weekend dates, the WORKDAY function knows to exclude those but you have to list any holiday dates that you want to exclude from the calculation. You simply enter those dates in a range of cells: J1: 1/1/2009 J2: 1/2/2009 J3: 2/21/2009 J4: 5/31/2009 J5: 7/4/2009 etc etc etc -- Biff Microsoft Excel MVP "NM" wrote in message ... What is the easiest way to set up a list of weekends and holidays? "T. Valko" wrote: Set up a list of holiday dates to be excluded. Assume this list is in the range J1:J10. Then, use this formula in column C: =WORKDAY(A1,B1,J1:J10) The WORKDAY function requires the Analysis ToolPak add-in be installed for versions of Excel prior to Excel 2007. -- Biff Microsoft Excel MVP "NM" wrote in message ... Hi, Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Calculate working days but change working week | Excel Discussion (Misc queries) | |||
Making weekend days working days - the system cuts the working tim | Excel Discussion (Misc queries) | |||
How to calculation no. of days (only working days) between two dat | Excel Discussion (Misc queries) | |||
Working days | Excel Discussion (Misc queries) | |||
Working Days | Excel Discussion (Misc queries) |