Sum working days
Set up a list of holiday dates to be excluded. Assume this list is in the
range J1:J10.
Then, use this formula in column C:
=WORKDAY(A1,B1,J1:J10)
The WORKDAY function requires the Analysis ToolPak add-in be installed for
versions of Excel prior to Excel 2007.
--
Biff
Microsoft Excel MVP
"NM" wrote in message
...
Hi,
Column A has date, Column B has number of days required to finish the
task,
in Column C I want to use a formula which adds Column B( number of days)
to
column A but excludes holidays and weekends and adds only working days.
eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 (
only working days to be added)
Thanks for your help.
|