Hi,
Column A has date, Column B has number of days required to finish the task, in Column C I want to use a formula which adds Column B( number of days) to column A but excludes holidays and weekends and adds only working days. eg. Column A has 12/8/08 Column B has 7 days coulmn C should be 12/17/08 ( only working days to be added) Thanks for your help. |