  #1   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 4
Default Project days allocation

i have a project that is 32 workdays and i want to spread the 32 work days by
month until the 32 days are used up. my project starts on random dates and
end on random deate and can cross multiple months. my fiscal months are not
calendar months. i have calculated how many work days there are in my fiscal
months so i want a formula that will "bounce" against the available days i
have to allocate. So, below i am looking for a formula that will calculate 2,
20 and 12 = 32

Jan Feb Mar
Apr May Jun
1/7-2/3 2/4-3/2 3/3-4/6
4/7-5/4 5/5-6/1 6/2-7/6
available days 20 20 25
20 20 25

--------------------------------------------------------------
proj start proj stop project duration

5/1/08 6/15/08 32 work days 0 0 2
20 12
  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
external usenet poster
 
Posts: 19
Default Project days allocation

See the response(s) to 'Project days allocation (better mail format)'

On Mon, 5 May 2008 05:45:02 -0700, dumbaswood
wrote:

i have a project that is 32 workdays and i want to spread the 32 work days by
month until the 32 days are used up. my project starts on random dates and
end on random deate and can cross multiple months. my fiscal months are not
calendar months. i have calculated how many work days there are in my fiscal
months so i want a formula that will "bounce" against the available days i
have to allocate. So, below i am looking for a formula that will calculate 2,
20 and 12 = 32

Jan Feb Mar
Apr May Jun
1/7-2/3 2/4-3/2 3/3-4/6
4/7-5/4 5/5-6/1 6/2-7/6
available days 20 20 25
20 20 25

--------------------------------------------------------------
proj start proj stop project duration

5/1/08 6/15/08 32 work days 0 0 2
20 12

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
find the beginning and end days of a project liu New Users to Excel 5 April 9th 08 12:44 AM
Calculate number days + hours to complete a project pfm Excel Worksheet Functions 1 January 23rd 08 02:29 AM
Excell error "Can't find Project or Library" Project VBAProject Lost in Excel Excel Worksheet Functions 0 April 12th 07 04:42 PM
How to convert MS Project to MS Excel. I don't have MS Project. Jane Excel Discussion (Misc queries) 1 February 20th 06 10:01 PM
F-key allocation HELLBOY787 Excel Discussion (Misc queries) 1 June 30th 05 11:21 AM


All times are GMT +1. The time now is 04:31 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"