#1
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Dear all,
i would like to change the Sunday as non-working day to be working day and change the friday to be non-working day. Can you help me pls?? Best regards |
#2
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
I guess that you mean that you want to do some sort of math with the changed
days. If it is just to calculate working days, use =SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(start_date&":"&end_date)),1) ={1,2,3,4,5})) -- --- HTH Bob (change the xxxx to gmail if mailing direct) "Mohammed" wrote in message ... Dear all, i would like to change the Sunday as non-working day to be working day and change the friday to be non-working day. Can you help me pls?? Best regards |
#3
![]()
Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
Some time ago I created an equivalent to WORKDAYS excel function
(EnchWorkaysN()), which allows you to determine which days of week are working days and which not. To have it work, you have to copy another 3 functions into your VBA module too. ------------------------------------------- Option Base 1 Function SelectionSort(TempArray As Variant) Dim MaxVal As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function sorts all entries in 1-dimensional array, ' it's a function provided in Microsoft KB article 133135 ' Step through the elements in the array starting with the ' last element in the array. For i = UBound(TempArray) To 1 Step -1 ' Set MaxVal to the element in the array and save the ' index of this element as MaxIndex. MaxVal = TempArray(i) MaxIndex = i ' Loop through the remaining elements to see if any is ' larger than MaxVal. If it is then set this element ' to be the new MaxVal. For j = 1 To i If TempArray(j) MaxVal Then MaxVal = TempArray(j) MaxIndex = j End If Next j ' If the index of the largest element is not i, then ' exchange this element with element i. If MaxIndex < i Then TempArray(MaxIndex) = TempArray(i) TempArray(i) = MaxVal End If Next i End Function Function SelectionUnique(TempArray As Variant, Optional AllowZeros As Boolean = True) Dim MaxVal, TempArray2() As Variant Dim MaxIndex As Integer Dim i, j As Integer ' The function is meant to work with ordered arrays ' and removes all double entries and Null values ' (Except when the is the only value, and it is Null). ' Optional argument determines, how 0 values are processed ' Initialize j = 1 ReDim TempArray2(1 To j) As Variant TempArray2(1) = Null ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Or _ IsEmpty(TempArray(i)) Or _ (TempArray(i) = 0 And AllowZeros = False) Then Else ' Redim TempArray2 and add an element ReDim Preserve TempArray2(1 To j) As Variant TempArray2(j) = TempArray(i) j = j + 1 ' Set CurrVal to the element in the array currval = TempArray(i) ' Cycle through next elements until value changes k = 0 If i < UBound(TempArray) Then Do While TempArray(i + k + 1) = currval k = k + 1 If i + k UBound(TempArray) Then Exit Do Loop End If i = Application.WorksheetFunction.Max(i, i + k - 1) End If Next i ' Write the passed array over TempArray = TempArray2 End Function Function SelectionToInteger(TempArray As Variant) Dim i As Integer ' The function cuts off decimal part from all non-empty elements of array ' Step through the elements in the array starting with the ' first element in the array. For i = 1 To UBound(TempArray) Step 1 If IsNull(TempArray(i)) Then Else ' Replace array element with it's integer value TempArray(i) = Int(TempArray(i)) End If Next i End Function Public Function EnchWorkdaysN(StartDate As Date, _ EndDate As Date, _ Optional Holidays As Variant = Nothing, _ Optional Weekends As Variant = Nothing, _ Optional WeekStart As Integer = 1) Dim arrayH As Variant, arrayW As Variant Dim di As Date, dn As Date, dx As Date ' The result doesn't depend on order of values of first 2 parameters. ' When parameter Holidays is omitted, or Null, or not a positive numeric (date) value, ' or not an array or cell range with numeric values, then no holidays ' are left out from day's count. ' When parameter Weekends is omitted, or Null, or not a numeric value =1 and <8, ' or not an array or cell range with at least one numeric value between =1 and <8, ' then 1 and 7 (Saturday and Sunday) are set for Weekend default walues, ' and according weekdays are left out from day's count. ' No weekends are left out from day's count (7-workday week) only then, ' when fourth parameter is set to FALSE. ' The parameter WeekStart determines, how are determined weekends in 4th parameter ' Allowed values for parameter WeekStart are integers 1 to 7. ' The number 1 indicates Sunday as 1st day of week, ' the number 2 indicates Monday as first day of week, etc. ' When the parameter WeekStart is not between 1 and 7, then WeekStart = (Abs(WeekStart) Mod 7)+1 ' Initialize ArrayH If TypeName(Holidays) = "Variant()" Then ReDim arrayH(1 To UBound(Holidays)) As Variant For i = 1 To UBound(Holidays) arrayH(i) = IIf(VarType(Holidays(i, 1)) 0 And VarType(Holidays(i, 1)) < 8, Holidays(i, 1), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf (VarType(Holidays) = 8192 And VarType(Holidays) <= 8199) Or _ VarType(Holidays) = 8204 Then ReDim arrayH(1 To UBound(Holidays.Value)) As Variant For i = 1 To UBound(Holidays.Value) arrayH(i) = IIf(VarType(Holidays(i)) 0 And VarType(Holidays(i)) < 8, Holidays(i), Null) arrayH(i) = IIf(arrayH(i) < 0, Null, arrayH(i)) Next i ElseIf VarType(Holidays) < 8 Then ReDim arrayH(1) As Variant arrayH(1) = Holidays arrayH(1) = IIf(arrayH(1) < 0, Null, arrayH(1)) Else ReDim arrayH(1) As Variant arrayH(1) = Null End If ' Sort arrayH SelectionSort arrayH ' Replace non-integer values with integers SelectionToInteger arrayH ' Remove double entries and empty elements SelectionUnique arrayH ' Initialize arrayW If VarType(Weekends) < 11 Then If TypeName(Weekends) = "Nothing" Then ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 ElseIf TypeName(Weekends) = "Variant()" Then ReDim arrayW(1 To UBound(Weekends)) As Variant For i = 1 To UBound(Weekends) If UBound(Weekends) = 1 Then arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) Else arrayW(i) = IIf(VarType(Weekends(i, 1)) 0 And VarType(Weekends(i, 1)) < 8, ((Abs(Weekends(i, 1)) + 12 + WeekStart) Mod 7) + 1, Null) End If arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf VarType(Weekends) = 8192 And VarType(Weekends) <= 8199 Or _ VarType(Weekends) = 8204 Then ReDim arrayW(1 To UBound(Weekends.Value)) As Variant For i = 1 To UBound(Weekends.Value) arrayW(i) = IIf(VarType(Weekends(i)) 0 And VarType(Weekends(i)) < 8, ((Abs(Weekends(i)) + 12 + WeekStart) Mod 7) + 1, Null) arrayW(i) = IIf(arrayW(i) < 1 Or arrayW(i) = 8, Null, arrayW(i)) Next i ElseIf (Int(Weekends) = 1 And Int(Weekends) < 8) Then ReDim arrayW(1) As Variant arrayW(1) = ((Abs(Weekends) + 12 + WeekStart) Mod 7) + 1 arrayW(1) = IIf(arrayW(1) < 1 Or arrayW(1) = 8, Null, arrayW(1)) Else ReDim arrayW(1 To 2) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Sort arrayW SelectionSort arrayW ' Replace non-integer values with integers SelectionToInteger arrayW ' Remove double entries and empty elements SelectionUnique arrayW, False Else ' Set 1st element to 0 for 7-workday week ReDim arrayW(1) As Variant arrayW(1) = IIf(Weekends = False, 0, Null) End If ' When empty array, insert default values If arrayW(1) = Null Then ReDim arrayW(1 To 2, 1) As Variant arrayW(1) = 1 arrayW(2) = 7 End If ' Calculate the number of workdays in date interval determined by StartDay and EndDay EnchWorkdaysN = 0 di = Application.WorksheetFunction.Min(StartDate, EndDate) dn = Application.WorksheetFunction.Max(StartDate, EndDate) dx = di Do While dx <= dn x = False i = 1 Do While x = False And i <= UBound(arrayH) And TypeName(arrayH(1)) < "Null" x = (dx = arrayH(i)) i = i + 1 Loop i = 1 Do While x = False And i <= UBound(arrayW) And arrayW(1) < 0 x = (Weekday(dx) = arrayW(i)) i = i + 1 Loop If Not (x) Then EnchWorkdaysN = EnchWorkdaysN + 1 dx = dx + 1 Loop End Function ------------------------------------------- -- Arvi Laanemets ( My real mail address: arvi.laanemets<attarkon.ee ) "Mohammed" wrote in message ... Dear all, i would like to change the Sunday as non-working day to be working day and change the friday to be non-working day. Can you help me pls?? Best regards |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
How do I add only business days in Excel formulas? | Excel Discussion (Misc queries) | |||
Alt+Tab doesn't work to change from excel file to excel file | Excel Discussion (Misc queries) | |||
adding only working days to dates | Excel Discussion (Misc queries) | |||
Add or Subtract Working Days in Excel | Excel Discussion (Misc queries) | |||
Days in Calender | Excel Discussion (Misc queries) |