Hello,

I have two cells A1 and B1, in A1 I have a date. In B1 I want that date
5 working days later (Monday to Friday).

Is this possible in 1 formula?

Thank you for your time.

;)


--
neway9
------------------------------------------------------------------------
neway9's Profile: http://www.excelforum.com/member.php...o&userid=17622
View this thread: http://www.excelforum.com/showthread...hreadid=560174

  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 1
Default Another Working day question!


Just add 5 in cell B1 (=a1+5) and drag the formula


--
blissworks
------------------------------------------------------------------------
blissworks's Profile: http://www.excelforum.com/member.php...o&userid=36156
View this thread: http://www.excelforum.com/showthread...hreadid=560174

  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 1
Default Another Working day question!


Hello,

Yeah, got that, but need it to be working days only.


--
neway9
------------------------------------------------------------------------
neway9's Profile: http://www.excelforum.com/member.php...o&userid=17622
View this thread: http://www.excelforum.com/showthread...hreadid=560174

  #4   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 1
Default Another Working day question!


Hi neway9,

Will this work?

= WORKDAY(A1,4)


--
keithl816
------------------------------------------------------------------------
keithl816's Profile: http://www.excelforum.com/member.php...o&userid=21287
View this thread: http://www.excelforum.com/showthread...hreadid=560174

  #5   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 1
Default Another Working day question!


Yeah, that works great,

Thank you!


--
neway9
------------------------------------------------------------------------
neway9's Profile: http://www.excelforum.com/member.php...o&userid=17622
View this thread: http://www.excelforum.com/showthread...hreadid=560174

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Graph from a PIVOT table: update not working. Please Help! Marcus Excel Discussion (Misc queries) 0 June 7th 05 05:53 PM
Working time and days Nortos Excel Worksheet Functions 5 May 6th 05 04:17 PM
Working time and days Nortos Excel Discussion (Misc queries) 1 May 6th 05 03:47 PM
Hints And Tips For New Posters In The Excel Newsgroups Gary Brown Excel Worksheet Functions 0 April 15th 05 05:47 PM
Trace Dependents and Precedents not working Manish Excel Worksheet Functions 0 April 11th 05 09:39 PM


All times are GMT +1. The time now is 03:43 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"