  #1   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 4
Default sumproduct with additions to data

I am using Sumproduct to count the number of parts delivered late to
schedule, but we have a 5 day grace period that I can't figure out how to
accommodate. What I need to do is add 5 days to the due date (X:X) then
determine if the receipt of the part (Y:Y) was later than that date.

what I have is:
=SUMPRODUCT(--(DATA!AE2:AE7500)=R6),--(DATA!X2:X7500<DATA!Y2:Y7500))

DATA! is the tab where the data is pulled into from their various legacy
systems
AE:AE is the vendor code (I am collecting the data by vendor)
X:X is the scheduled due date
Y:Y is the actual receipt date

Sample Data: (we can assume all of them to be from the same vendor)

1. X(Due) Y(Reciept)
2. 05/04/09 05/05/09
3. 06/05/09 05/27/09
4. 08/30/09 04/06/09
5. 03/31/09 04/01/09
6. 04/03/09 04/06/09

Currently I would get a result of 3 of the 5 delivered parts being late (2,
5, and 6), but since all of them were delivered within the 5 day grace period
I should show a result of 0 being late. I cannot figure out how to add 5 days
to the scheduled date to accommodate the grace period and not unduly burden
our suppliers with inaccurate metrics.

Any help is appreciated.
  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 135
Default sumproduct with additions to data

Qikslvr -

Try this:

=SUMPRODUCT(--(DATA!AE2:AE7500)=R6),--(DATA!X2:X7500<DATA!Y2:Y7500 + 5))

--
Daryl S


"Qikslvr" wrote:

I am using Sumproduct to count the number of parts delivered late to
schedule, but we have a 5 day grace period that I can't figure out how to
accommodate. What I need to do is add 5 days to the due date (X:X) then
determine if the receipt of the part (Y:Y) was later than that date.

what I have is:
=SUMPRODUCT(--(DATA!AE2:AE7500)=R6),--(DATA!X2:X7500<DATA!Y2:Y7500))

DATA! is the tab where the data is pulled into from their various legacy
systems
AE:AE is the vendor code (I am collecting the data by vendor)
X:X is the scheduled due date
Y:Y is the actual receipt date

Sample Data: (we can assume all of them to be from the same vendor)

1. X(Due) Y(Reciept)
2. 05/04/09 05/05/09
3. 06/05/09 05/27/09
4. 08/30/09 04/06/09
5. 03/31/09 04/01/09
6. 04/03/09 04/06/09

Currently I would get a result of 3 of the 5 delivered parts being late (2,
5, and 6), but since all of them were delivered within the 5 day grace period
I should show a result of 0 being late. I cannot figure out how to add 5 days
to the scheduled date to accommodate the grace period and not unduly burden
our suppliers with inaccurate metrics.

Any help is appreciated.

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Useful Additions Ron100 Excel Discussion (Misc queries) 1 January 13th 10 01:38 PM
Additions Marc Excel Discussion (Misc queries) 1 November 11th 09 05:35 AM
Can I allow Additions but not Edits? Keith Excel Discussion (Misc queries) 2 November 9th 06 01:10 PM
Cell Additions acopper57 via OfficeKB.com Excel Worksheet Functions 0 May 17th 06 11:54 PM
Multiple additions BIYB Excel Discussion (Misc queries) 4 July 26th 05 04:22 PM


All times are GMT +1. The time now is 10:56 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"