workday calculation for backwards
I have already set up the scheduled completion date and working duration,
want a fomula to calculate the scheduled start date(work day). eg: A B C Start Date Duration Complete date 10 30-Oct-09 I need to know which workday on the columu "A" . Thanks. |
#2
Posted to microsoft.public.excel.misc
|
|||
|
|||
workday calculation for backwards
=WORKDAY(C1,-B1)
Format as Date If you get a #NAME error: ToolsAdd-insCheck Analysis Toolpak -- Kind regards, Niek Otten Microsoft MVP - Excel "Oscar" wrote in message ... I have already set up the scheduled completion date and working duration, want a fomula to calculate the scheduled start date(work day). eg: A B C Start Date Duration Complete date 10 30-Oct-09 I need to know which workday on the columu "A" . Thanks. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Workday calculation | Excel Discussion (Misc queries) | |||
Backwards LookUp | Excel Discussion (Misc queries) | |||
The A,B,C,D at the top of my page are backwards | Excel Discussion (Misc queries) | |||
Workday Date Calculation | Excel Worksheet Functions | |||
Workday calculation - not working | Excel Worksheet Functions |