workday calculation for backwards
I have already set up the scheduled completion date and working duration,
want a fomula to calculate the scheduled start date(work day). eg: A B C Start Date Duration Complete date 10 30-Oct-09 I need to know which workday on the columu "A" . Thanks. |
workday calculation for backwards
=WORKDAY(C1,-B1)
Format as Date If you get a #NAME error: ToolsAdd-insCheck Analysis Toolpak -- Kind regards, Niek Otten Microsoft MVP - Excel "Oscar" wrote in message ... I have already set up the scheduled completion date and working duration, want a fomula to calculate the scheduled start date(work day). eg: A B C Start Date Duration Complete date 10 30-Oct-09 I need to know which workday on the columu "A" . Thanks. |