I have the need to calculate 4 weekly periods with the periods starting on a
Thursday (historical reasoning) as follows:
Period 1 Start-29th May End-25th June
Period 2 Start-26th June End-23rd July

I have found out how to do this with Access but the same functions are not
available in Excel

Many thanks in advance
  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 2
Default Custom 4 week periods

My Mistake

Periods run from a Friday not a Thursday



"dazza_dog" wrote:

I have the need to calculate 4 weekly periods with the periods starting on a
Thursday (historical reasoning) as follows:
Period 1 Start-29th May End-25th June
Period 2 Start-26th June End-23rd July

I have found out how to do this with Access but the same functions are not
available in Excel

Many thanks in advance

  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 1
Default Custom 4 week periods


You say you want to calculate 4 week periods. I'm not sure what that
means, you just want a list?

If you put the start date of period 1 in B2, i.e. 29-May-2009 then C2
will calculate the end date with the formula

=B2+27

then in B3 you can use the formula

=B2+28

and then copy that formula across to C3 and down both columns as far as
you need. Format all cells in the required date format


--
barry houdini
------------------------------------------------------------------------
barry houdini's Profile: http://www.thecodecage.com/forumz/member.php?userid=72
View this thread: http://www.thecodecage.com/forumz/sh...d.php?t=108599

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Generate list of dates for 4-week periods Karie Excel Discussion (Misc queries) 1 January 12th 09 08:48 PM
Special custom fill function which adds periods at the end of text JTA Excel Discussion (Misc queries) 1 April 1st 08 11:25 PM
HOW to calculate the interest paid between 2 custom periods? TiDz Excel Worksheet Functions 1 June 30th 06 12:46 PM
Custom Date format ie. 01.01.05 W1 (W1 is week 1) aspen Excel Discussion (Misc queries) 3 December 29th 04 04:23 AM
How do I make a Custom Datre Format ie 01.01.05 WK1 (WK is Week 1) sorry about previous post aspen Excel Discussion (Misc queries) 0 December 29th 04 01:05 AM


All times are GMT +1. The time now is 09:29 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"