Hello All, I am working with a spreadsheet that contains a Field called
"Resolve by Date" This date is computed in the application that is supplying
the raw data. What I am trying to do is this: Use the "Resolve by Date" to
determine the date that the request was submitted. I know that this "Resolve
by Date" is 15 networkdays from the date the request was submitted. How do I
back into this "Submit" date using the networkdays function? It appears
simple, but the answer is escaping me! Any guidance would be greatly
appreciated. D.

  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 11,501
Default Reverse Networkdays??

Hi

With your resolve by date in A1 try

=workday(A1,-15)

Format as date

Mike

"Drayton T." wrote:

Hello All, I am working with a spreadsheet that contains a Field called
"Resolve by Date" This date is computed in the application that is supplying
the raw data. What I am trying to do is this: Use the "Resolve by Date" to
determine the date that the request was submitted. I know that this "Resolve
by Date" is 15 networkdays from the date the request was submitted. How do I
back into this "Submit" date using the networkdays function? It appears
simple, but the answer is escaping me! Any guidance would be greatly
appreciated. D.

  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 2
Default Reverse Networkdays??

DOH!

Man..do I feel stupid.

thanks! D.

"Mike H" wrote:

Hi

With your resolve by date in A1 try

=workday(A1,-15)

Format as date

Mike

"Drayton T." wrote:

Hello All, I am working with a spreadsheet that contains a Field called
"Resolve by Date" This date is computed in the application that is supplying
the raw data. What I am trying to do is this: Use the "Resolve by Date" to
determine the date that the request was submitted. I know that this "Resolve
by Date" is 15 networkdays from the date the request was submitted. How do I
back into this "Submit" date using the networkdays function? It appears
simple, but the answer is escaping me! Any guidance would be greatly
appreciated. D.

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Networkdays Lyn Excel Discussion (Misc queries) 6 August 21st 08 04:04 PM
using NETWORKDAYS mandy Excel Discussion (Misc queries) 9 May 2nd 07 10:03 AM
Networkdays Dave Excel Discussion (Misc queries) 3 January 13th 07 04:58 PM
Reverse NETWORKDAYS function? [email protected] Excel Worksheet Functions 4 October 4th 06 01:49 PM
NETWORKDAYS = 0 ann Excel Discussion (Misc queries) 4 October 3rd 05 10:07 PM


All times are GMT +1. The time now is 02:07 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"