I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.
  #2   Report Post  
Frank Kabel
 
Posts: n/a
Default

Hi
use NETWORKDAYS for this (note: you have to install the Analysis Toolpak for
this)

"mpetersen" wrote:

I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.

  #3   Report Post  
Jason Morin
 
Posts: n/a
Default

Use the NETWORKDAYS worksheet function. See XL help.

HTH
Jason
Atlanta, GA



-----Original Message-----
I am trying to calculate production days in Excel

instead of calendar days.
Is there a way to do this? That is to say if I start a

project on October 1,
2004 and finish it December 13, 2004 I would like to

know how many days that
this project was actually worked.

Production days are usually just the days of the week,

less any holidays
that are able to be worked.

Thanks for any assistance you can offer.
.

  #4   Report Post  
Domenic
 
Posts: n/a
Default

If "just the days of the week" excludes weekends...

=NETWORKDAYS(StartDate,EndDate,Holidays)

....where Holidays refers to one or more dates to exclude from the
calculation.

Hope this helps!

In article ,
mpetersen wrote:

I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Excel aficionado wants to learn Access Hari Excel Discussion (Misc queries) 0 December 3rd 04 07:03 AM
Excel aficionado wants to learn Access Hari Excel Discussion (Misc queries) 0 December 3rd 04 06:47 AM
Excel aficionado wants to learn Access Hari Excel Discussion (Misc queries) 0 December 3rd 04 06:45 AM
Excel user desires to learn ABC of Access Hari Excel Discussion (Misc queries) 1 December 3rd 04 03:32 AM
OPENING TWO DIFFERENT EXCEL PROGRAMS EXCEL SPREADSHEETS Excel Discussion (Misc queries) 3 December 3rd 04 12:14 AM


All times are GMT +1. The time now is 10:24 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"