ExcelBanter

ExcelBanter (https://www.excelbanter.com/)
-   Excel Discussion (Misc queries) (https://www.excelbanter.com/excel-discussion-misc-queries/)
-   -   Calculating Production/Man Days in Excel (https://www.excelbanter.com/excel-discussion-misc-queries/2020-calculating-production-man-days-excel.html)

mpetersen

Calculating Production/Man Days in Excel
 
I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.

Frank Kabel

Hi
use NETWORKDAYS for this (note: you have to install the Analysis Toolpak for
this)

"mpetersen" wrote:

I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.


Jason Morin

Use the NETWORKDAYS worksheet function. See XL help.

HTH
Jason
Atlanta, GA



-----Original Message-----
I am trying to calculate production days in Excel

instead of calendar days.
Is there a way to do this? That is to say if I start a

project on October 1,
2004 and finish it December 13, 2004 I would like to

know how many days that
this project was actually worked.

Production days are usually just the days of the week,

less any holidays
that are able to be worked.

Thanks for any assistance you can offer.
.


Domenic

If "just the days of the week" excludes weekends...

=NETWORKDAYS(StartDate,EndDate,Holidays)

....where Holidays refers to one or more dates to exclude from the
calculation.

Hope this helps!

In article ,
mpetersen wrote:

I am trying to calculate production days in Excel instead of calendar days.
Is there a way to do this? That is to say if I start a project on October 1,
2004 and finish it December 13, 2004 I would like to know how many days that
this project was actually worked.

Production days are usually just the days of the week, less any holidays
that are able to be worked.

Thanks for any assistance you can offer.



All times are GMT +1. The time now is 03:09 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
ExcelBanter.com