Default Calculating and listing only Monday-Friday in a work schedule

Thanks!
I will document this and use it now and have it saved for the future.
I really find the Excel Newsgroup an outstanding resource.
Again, thanks to all !
Jugglertwo

"Gord Dibben" wrote:

I would say the WORKDAY function would be what you want.

=WORKDAY(startdate,numberofdays)

A1..............Jan1, 2008

B1...............36

C1.................=WORKDAY(A1,B1) returns February 20, 2008 assuming no
holidays in that period.

For second part, enter in A2 =A1+1 and drag/copy down until you get Feb 20,
2008


Gord



On Sun, 20 Apr 2008 10:23:00 -0700, Jugglertwo
wrote:

Thanks to both of you for suggesting the two different functions.
I should have explained further that I have been trying to figure it out
with the =NETWORKDAYS function but that is basically my question.

How do I utilized the =NETWORKDAYS to give a starting date with the number
of days that it will require for the house to be completed?

I just haven't been able to figure out the way to utilize the function
correctly.
Thanks and I will keep plugging.
Jugglerwo

"Gord Dibben" wrote:

See help on the NETWORKDAYS function from the Analysis Toolpak


Gord Dibben MS Excel MVP

On Sat, 19 Apr 2008 19:12:00 -0700, Jugglertwo
wrote:

Here are two question that a student recently asked.
They build houses. They only work weekdays, Monday-Friday.

1) Question 1: They want to put in a starting date in one cell and put the
number of days it will take to complete the house in another cell. They want
to know on what date the house will be finished. What calculation will allow
this to happen?

2) Question 2: How can they list the starting date through the finishing
date so they can note work progress on a daily basis?

Any suggestions would be greatly appreciated. thanks!
Jugglertwo




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Help change Friday to following Monday David Excel Discussion (Misc queries) 4 June 22nd 06 01:24 AM
calculating adjacent columns in a work schedule CCsoccer14 Excel Worksheet Functions 1 June 15th 06 06:30 PM
calculating adjacent columns in a work schedule HB Designs Excel Worksheet Functions 0 June 15th 06 06:23 PM
calculating adjacent columns in a work schedule HB Designs Excel Worksheet Functions 0 June 15th 06 06:23 PM
Calculating first/last Monday, Tuesday, etc. in a given month in E Rossta Excel Worksheet Functions 3 May 27th 06 02:19 AM


All times are GMT +1. The time now is 05:34 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"