I shall try to explain!!!
I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#2
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
kk,
Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#3
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Hi Conan,
Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#5
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Thanks Sandy,
Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#6
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
If no one else gives you an answer I will have a look at it tomorrow. What
date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#7
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Thanks Sandy,
Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#8
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
I'm not the best VBA programmer - that is why I was hoping that someone with
more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month of its expiry date the start date wil still be the same. ie with the same example...had I renewed within 3 month prior to the end of Jan, the expiry date will be the same (31 july). I hope that makes sense!! How can that be written in vb code? -- kk |
#9
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Thanks fir that Sandy,
I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any time at the first month. ie if I renewed on the 20th of Jan then the run out date will be 31 July. Now to complicate things. I can renew a certificate within 3 month |
#10
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
I cant get the code to work, but I think I can work with the formula.
Thanks very much for your help. -- kk "kk" wrote: Thanks fir that Sandy, I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any |
#11
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
What does *I cant get the code to work* mean? Nothing happens? Gives
incorrect results? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... I cant get the code to work, but I think I can work with the formula. Thanks very much for your help. -- kk "kk" wrote: Thanks fir that Sandy, I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like you guys are ripping people off!!! :-D (or <vbg) Please provide more information. Is Start Date coming from a cell? Is Renew Date coming from a cell? Are you trying to put Expiration Date in a cell? Are you trying to create a UDF to return Expiration Date to a cell? Are you trying to update values in current cells or are you adding rows to a table with these new values? Please post the code you have so far. How can that be written in vb code? I don't know how that can be written in VBA until I know what you are trying to do. HTH, Conan "kk" wrote in message ... I shall try to explain!!! I keep a record of certificate dates. These certificates are valid for six month only and have to be renewed every time. The certificate end date will always be at the end of the sixth month, but the start can be at any |
#12
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Nothing happens.
Maybe I have placed it in the wrong place! -- kk "Sandy Mann" wrote: What does *I cant get the code to work* mean? Nothing happens? Gives incorrect results? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... I cant get the code to work, but I think I can work with the formula. Thanks very much for your help. -- kk "kk" wrote: Thanks fir that Sandy, I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like |
#13
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Hi kk,
First of all you must have Macros enabled to run the code: Tools Macro Security select *Medium* or *Low,* (but Low is not recommended) Right-click on the Sheet Tab and select *View Code.* Select Insert Module (or press and hold Alt while you press I and then M) This will insert a new Module 1. Copy and paste the code into this module. Close and reopen the workbook and you sould be asked to Eable Macros. Select: Tools Options Macros and either select the Macro and click on Run or Click on the *Options* button instead of the Macro and then in the *Macro Options* dialog box enter the shortcut key that you want to run the Macro from and click on OK then the *Cancel* button on the Macro dialog box. The Macro will now run if you press had hold the Ctrl key while you press the shortcut key. Note: The Shortcut key is case sensitive and don't pick a key that you want to use for some other function, (ie if you select c then ctrl + c will no longer copy data). Post back if you are still having trouble. -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Nothing happens. Maybe I have placed it in the wrong place! -- kk "Sandy Mann" wrote: What does *I cant get the code to work* mean? Nothing happens? Gives incorrect results? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... I cant get the code to work, but I think I can work with the formula. Thanks very much for your help. -- kk "kk" wrote: Thanks fir that Sandy, I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of that date, but the new renewal date will always be 6month from the original expiry date. ( I`m getting confused myself!!!!!!)......to give an example: A B Start date Expiry date 09-Nov-07 31-May-08 Case 1: If I renew on any day in May then my next renewal date will be 30-Nov-08 Case 2: If I renew on any day between 1st Mar and the end of May then my next renewal date will be 30-Nov-08. Case 3: If I let it lapse and renew on any day say in June then my next renewal date will be 30-Dec-08 Incidentally, no money is charged.....all free!!!!! I hope that has answered any confusions! -- kk "Conan Kelly" wrote: kk, Let me get this straight. I can renew for 6 more months from May 1st to July 31st, but my start date will still be Jan 20th and my Expiration date will still be July 31st, thus requiring me to renew AGAIN for 6 more months after July 31st? Is there a charge to renew? If so, what company do you work for. I'll be sure that I never require your services. It sounds like |
#14
![]()
Posted to microsoft.public.excel.misc
|
|||
|
|||
![]()
Thanks Sandy,
I will give it a go and let you know how I get on. -- kk "Sandy Mann" wrote: Hi kk, First of all you must have Macros enabled to run the code: Tools Macro Security select *Medium* or *Low,* (but Low is not recommended) Right-click on the Sheet Tab and select *View Code.* Select Insert Module (or press and hold Alt while you press I and then M) This will insert a new Module 1. Copy and paste the code into this module. Close and reopen the workbook and you sould be asked to Eable Macros. Select: Tools Options Macros and either select the Macro and click on Run or Click on the *Options* button instead of the Macro and then in the *Macro Options* dialog box enter the shortcut key that you want to run the Macro from and click on OK then the *Cancel* button on the Macro dialog box. The Macro will now run if you press had hold the Ctrl key while you press the shortcut key. Note: The Shortcut key is case sensitive and don't pick a key that you want to use for some other function, (ie if you select c then ctrl + c will no longer copy data). Post back if you are still having trouble. -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Nothing happens. Maybe I have placed it in the wrong place! -- kk "Sandy Mann" wrote: What does *I cant get the code to work* mean? Nothing happens? Gives incorrect results? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... I cant get the code to work, but I think I can work with the formula. Thanks very much for your help. -- kk "kk" wrote: Thanks fir that Sandy, I shall give it a try and let you know how I get on. -- kk "Sandy Mann" wrote: I'm not the best VBA programmer - that is why I was hoping that someone with more skills would jump in - but try this code: Option Explicit Sub TestDate() Dim InDate As String Dim Idate As Long Dim EDate As Long Dim Ans As Integer Dim eEDate As Long Dim NexDate As Long Dim ExDate As String Dim EYear As Long Dim EMonth As Long Dim LastRow As Long InDateInput: On Error GoTo 0 InDate = _ InputBox("Please enter the date of the " & _ "Test in the format d-mmm-yy", "Test Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(InDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo InDateInput End If Idate = DateValue(InDate) Ans = MsgBox("Test Date was: " & _ Format(Idate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Test Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo InDateInput ExDateInput: On Error GoTo 0 ExDate = _ InputBox("Please enter the date of the last " & _ "Expiry in the format dd-mmm-yy", "Expiry Date") 'Change the dd/mm/yy to the date system you use On Error Resume Next If IsError(DateValue(ExDate)) Then MsgBox "I don't recognise that as a date" & vbLf & _ "Please try again" GoTo ExDateInput End If EDate = DateValue(ExDate) Ans = MsgBox("Last Expiry Date is: " _ & Format(EDate, "d-mmm-yy") & vbLf & _ "Is That correct?", vbYesNo, "Expiry Date") 'Change the Format to the date format that you use If Ans = 7 Then GoTo ExDateInput EYear = Year(EDate): EMonth = Month(EDate) - 2 eEDate = DateValue(1 & "/" & EMonth & "/" & EYear) If Idate EDate Then MsgBox "There is a mistake in one of the dates" & vbLf & _ "Please start again", , "Date Error!" GoTo InDateInput End If If eEDate = Idate Then MsgBox "You have taken the Test too early", _ , "Test taken too soon" Exit Sub End If EMonth = Month(EDate) + 7 If EMonth 12 Then EMonth = EMonth - 12 EYear = EYear + 1 End If NexDate = DateValue(1 & "/" & EMonth & "/" & EYear) NexDate = NexDate - 1 MsgBox "New Expiry Date is: " _ & Format(NexDate, "d-mmm-yy"), , "New Expiry Date" Ans = MsgBox("Enter the new dates in the Spreadsheet?", _ vbYesNo, "Update Spreadsheet") If Ans = 6 Then With ActiveSheet Columns("A:B").ColumnWidth = 13 Columns("A:B").NumberFormat = "d-mmm-yy" End With Cells(1, 1).Value = "Test Date" Cells(1, 2).Value = "Expiry Date" LastRow = Cells(Rows.Count, 2).End(xlUp).Row + 1 Cells(LastRow, 1).Value = Idate Cells(LastRow, 2).Value = NexDate End If End Sub Note that because the focus is on the *Yes* button just pressing *Enter* will accept the option and although it says to enter the date in the format "d-mmm-yy" it also accepts "d/mm/yy" -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Im using the following format "dd-mmm-yy" -- kk "Sandy Mann" wrote: If no one else gives you an answer I will have a look at it tomorrow. What date system do you use, American or British? -- Regards, Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Thanks Sandy, Is there a vb code to do the same? -- kk "Sandy Mann" wrote: With the 1st Start Date in A2, and the Expiry Date in B2, the next expiry date in B3 is: =IF(A3="","",IF(DATE(YEAR(B2),MONTH(B2)-2,0)+1<=A3,MAX(DATE(YEAR(A3),MONTH(A3)+7,0),DATE(Y EAR(B2),MONTH(B2)+7,0)),"Too Early")) For all three of your scenarios -- HTH Sandy In Perth, the ancient capital of Scotland and the crowning place of kings Replace @mailinator.com with @tiscali.co.uk "kk" wrote in message ... Hi Conan, Ok here we go!!!! I work in the aviation world as a pilot. Every 6 month we have to do a test (which generates a certificate to say we have completed and passed this test). I have a form (using excel) which I keep a record of these dates. Cell "A2"= date test taken, Cell "A2"= test expires (this date will always be the last date of the month). We have to renew before the expiry date and that will give us another 6 month. Now, One can elect to renew before the expiry date, and this can be done within 3 month of |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Date Question | Excel Worksheet Functions | |||
Date question | Excel Worksheet Functions | |||
Date Question | Excel Discussion (Misc queries) | |||
Date Question | Excel Discussion (Misc queries) | |||
Another Date Question | Excel Discussion (Misc queries) |