#1
Posted to microsoft.public.excel.misc
|
|||
|
|||
Calculating working days
Hi,
Does anyone know how to calculate working days? I try =workdays(start date, end date) but it gives me an error #NAME message. Thanks |
#2
Posted to microsoft.public.excel.misc
|
|||
|
|||
Calculating working days
Use the following function to calculate working days:
=NETWORKDAYS(StartDateValue,EndDateValue) This formula calculates only the Monday through Friday dates. Optionally, you can enter a range of dates for your holidays so that they are not counted as working day. If your start date is in A1, the end dat is in B1 and the range of holiday dates is F1:F10 the formula would look like this: =NETWORKDAYS(A1,B1,F1:F10) -- Kevin Backmann "SA" wrote: Hi, Does anyone know how to calculate working days? I try =workdays(start date, end date) but it gives me an error #NAME message. Thanks |
#3
Posted to microsoft.public.excel.misc
|
|||
|
|||
Calculating working days
Thanks for the help. I did try the networkdays formula and it did not work
either. I also tried to add in Analysis TookPak into my Excel 2002 and it's added but the error message is still the same. Have I missed anything? "Kevin B" wrote: Use the following function to calculate working days: =NETWORKDAYS(StartDateValue,EndDateValue) This formula calculates only the Monday through Friday dates. Optionally, you can enter a range of dates for your holidays so that they are not counted as working day. If your start date is in A1, the end dat is in B1 and the range of holiday dates is F1:F10 the formula would look like this: =NETWORKDAYS(A1,B1,F1:F10) -- Kevin Backmann "SA" wrote: Hi, Does anyone know how to calculate working days? I try =workdays(start date, end date) but it gives me an error #NAME message. Thanks |
#4
Posted to microsoft.public.excel.misc
|
|||
|
|||
Calculating working days
Have you been able to physically locate the add-ins on the drive. I don't
remember the exact path for the add-ins for Excel 2002, but it might be very similar to the following: C:\Program Files\microsoft office\OFFICE11\Library\Analysis The analysis toolpack is named ATPVBAEN.XLA in 2003, but I'm fairly certain that it's the same. -- Kevin Backmann "SA" wrote: Thanks for the help. I did try the networkdays formula and it did not work either. I also tried to add in Analysis TookPak into my Excel 2002 and it's added but the error message is still the same. Have I missed anything? "Kevin B" wrote: Use the following function to calculate working days: =NETWORKDAYS(StartDateValue,EndDateValue) This formula calculates only the Monday through Friday dates. Optionally, you can enter a range of dates for your holidays so that they are not counted as working day. If your start date is in A1, the end dat is in B1 and the range of holiday dates is F1:F10 the formula would look like this: =NETWORKDAYS(A1,B1,F1:F10) -- Kevin Backmann "SA" wrote: Hi, Does anyone know how to calculate working days? I try =workdays(start date, end date) but it gives me an error #NAME message. Thanks |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Conditional Formatting Dates calculating 10 days and 30 days from a certain date | Excel Worksheet Functions | |||
Calculating three working days before a date | Excel Worksheet Functions | |||
Calculating Working Days - Department of Pathology | Excel Discussion (Misc queries) | |||
Calculating recurring date in following month, calculating # days in that period | Excel Worksheet Functions | |||
Calculating Working Days | Excel Worksheet Functions |