Dear Super Excel Expert,
I am working in a company in Dubai where I am trying to monitor the lead time of order preparation. I have in column A the order date and time in DD:MM:YY HH:MM and in column B the packed date and time (same format). I would like to have in column C the leadtime between A and B in the following format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends which are Fridays and Saturdays. Exple : A1 = 27/06/07 09:43 B1 = 01/07/07 11:05 29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded. C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes). Please, you will be saving me a lot of my time. Thanks again. Excel Dubai |
#2
Posted to microsoft.public.excel.misc
|
|||
|
|||
How to calculate lead time excluding Friday and Saturday
It's not that simple
http://www.cpearson.com/excel/DateTimeWS.htm -- Regards, Peo Sjoblom Excel 95 - Excel 2007 Northwest Excel Solutions www.nwexcelsolutions.com (Remove ^^ from email) "Excel Dubai" wrote in message ... Dear Super Excel Expert, I am working in a company in Dubai where I am trying to monitor the lead time of order preparation. I have in column A the order date and time in DD:MM:YY HH:MM and in column B the packed date and time (same format). I would like to have in column C the leadtime between A and B in the following format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends which are Fridays and Saturdays. Exple : A1 = 27/06/07 09:43 B1 = 01/07/07 11:05 29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded. C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes). Please, you will be saving me a lot of my time. Thanks again. Excel Dubai |
#3
Posted to microsoft.public.excel.misc
|
|||
|
|||
How to calculate lead time excluding Friday and Saturday
Dear Peo,
Thanks a lot. It's great ! It's working. Regards, Excel Dubai. "Peo Sjoblom" wrote: It's not that simple http://www.cpearson.com/excel/DateTimeWS.htm -- Regards, Peo Sjoblom Excel 95 - Excel 2007 Northwest Excel Solutions www.nwexcelsolutions.com (Remove ^^ from email) "Excel Dubai" wrote in message ... Dear Super Excel Expert, I am working in a company in Dubai where I am trying to monitor the lead time of order preparation. I have in column A the order date and time in DD:MM:YY HH:MM and in column B the packed date and time (same format). I would like to have in column C the leadtime between A and B in the following format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends which are Fridays and Saturdays. Exple : A1 = 27/06/07 09:43 B1 = 01/07/07 11:05 29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded. C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes). Please, you will be saving me a lot of my time. Thanks again. Excel Dubai |
#4
Posted to microsoft.public.excel.misc
|
|||
|
|||
How to calculate lead time excluding Friday and Saturday
Dear Peo,
Thanks it's great ! Regards, Excel Dubai "Peo Sjoblom" wrote: It's not that simple http://www.cpearson.com/excel/DateTimeWS.htm -- Regards, Peo Sjoblom Excel 95 - Excel 2007 Northwest Excel Solutions www.nwexcelsolutions.com (Remove ^^ from email) "Excel Dubai" wrote in message ... Dear Super Excel Expert, I am working in a company in Dubai where I am trying to monitor the lead time of order preparation. I have in column A the order date and time in DD:MM:YY HH:MM and in column B the packed date and time (same format). I would like to have in column C the leadtime between A and B in the following format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends which are Fridays and Saturdays. Exple : A1 = 27/06/07 09:43 B1 = 01/07/07 11:05 29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded. C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes). Please, you will be saving me a lot of my time. Thanks again. Excel Dubai |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
How do I set NETWORKDAYS to regard friday and saturday as weekend | Excel Worksheet Functions | |||
Calculate lead time for a non european country | Excel Discussion (Misc queries) | |||
Calculate time (excluding weekend (48 hrs)) | Excel Worksheet Functions | |||
Starting work period on a Saturday and ending on a friday | Excel Worksheet Functions | |||
Starting work period on a Saturday and ending on a friday | Excel Discussion (Misc queries) |