Dear Super Excel Expert,

I am working in a company in Dubai where I am trying to monitor the lead
time of order preparation. I have in column A the order date and time in
DD:MM:YY HH:MM and in column B the packed date and time (same format). I
would like to have in column C the leadtime between A and B in the following
format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends
which are Fridays and Saturdays. Exple :
A1 = 27/06/07 09:43
B1 = 01/07/07 11:05
29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded.
C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes).

Please, you will be saving me a lot of my time.
Thanks again.

Excel Dubai
  #2   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 299
Default How to calculate lead time excluding Friday and Saturday

It's not that simple

http://www.cpearson.com/excel/DateTimeWS.htm



--


Regards,

Peo Sjoblom

Excel 95 - Excel 2007
Northwest Excel Solutions
www.nwexcelsolutions.com
(Remove ^^ from email)


"Excel Dubai" wrote in message
...
Dear Super Excel Expert,

I am working in a company in Dubai where I am trying to monitor the lead
time of order preparation. I have in column A the order date and time in
DD:MM:YY HH:MM and in column B the packed date and time (same format). I
would like to have in column C the leadtime between A and B in the
following
format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends
which are Fridays and Saturdays. Exple :
A1 = 27/06/07 09:43
B1 = 01/07/07 11:05
29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded.
C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes).

Please, you will be saving me a lot of my time.
Thanks again.

Excel Dubai



  #3   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 10
Default How to calculate lead time excluding Friday and Saturday

Dear Peo,

Thanks a lot. It's great ! It's working.


Regards,

Excel Dubai.

"Peo Sjoblom" wrote:

It's not that simple

http://www.cpearson.com/excel/DateTimeWS.htm



--


Regards,

Peo Sjoblom

Excel 95 - Excel 2007
Northwest Excel Solutions
www.nwexcelsolutions.com
(Remove ^^ from email)


"Excel Dubai" wrote in message
...
Dear Super Excel Expert,

I am working in a company in Dubai where I am trying to monitor the lead
time of order preparation. I have in column A the order date and time in
DD:MM:YY HH:MM and in column B the packed date and time (same format). I
would like to have in column C the leadtime between A and B in the
following
format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends
which are Fridays and Saturdays. Exple :
A1 = 27/06/07 09:43
B1 = 01/07/07 11:05
29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded.
C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes).

Please, you will be saving me a lot of my time.
Thanks again.

Excel Dubai




  #4   Report Post  
Posted to microsoft.public.excel.misc
external usenet poster
 
Posts: 10
Default How to calculate lead time excluding Friday and Saturday

Dear Peo,

Thanks it's great !

Regards,

Excel Dubai

"Peo Sjoblom" wrote:

It's not that simple

http://www.cpearson.com/excel/DateTimeWS.htm



--


Regards,

Peo Sjoblom

Excel 95 - Excel 2007
Northwest Excel Solutions
www.nwexcelsolutions.com
(Remove ^^ from email)


"Excel Dubai" wrote in message
...
Dear Super Excel Expert,

I am working in a company in Dubai where I am trying to monitor the lead
time of order preparation. I have in column A the order date and time in
DD:MM:YY HH:MM and in column B the packed date and time (same format). I
would like to have in column C the leadtime between A and B in the
following
format : DD:HH:MM excluding Holidays (in a separate sheet) and week ends
which are Fridays and Saturdays. Exple :
A1 = 27/06/07 09:43
B1 = 01/07/07 11:05
29/06/07 and 30/06/07 are Fridays and Saturdays and therefore excluded.
C1 should be equal to 02:01:22 (= 2days + 1 Hour + 22 minutes).

Please, you will be saving me a lot of my time.
Thanks again.

Excel Dubai




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
How do I set NETWORKDAYS to regard friday and saturday as weekend Shay.C. Excel Worksheet Functions 2 April 13th 10 05:13 PM
Calculate lead time for a non european country Excel Dubai[_2_] Excel Discussion (Misc queries) 1 March 20th 07 01:12 PM
Calculate time (excluding weekend (48 hrs)) AndyO_UK Excel Worksheet Functions 10 February 3rd 07 07:55 PM
Starting work period on a Saturday and ending on a friday JLyons Excel Worksheet Functions 3 February 18th 05 01:13 PM
Starting work period on a Saturday and ending on a friday JLyons Excel Discussion (Misc queries) 1 February 17th 05 02:28 PM


All times are GMT +1. The time now is 02:58 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"