I need to standardize a multitude of graphs so they can be compared.
The time in minutes (Length) along the vertical axis and the time of day (Oper. Starts) along the horizontal axis should be constant/same for all graphs and the values plotted against those set numbers. In this case data points are from 8:00 to 13:00 and values are from 0 to 5 minutes. Is it possible to have all the tables for different days of equal length? How? Oper. Starts Length 8:09:20 02:10 8:50:30 01:47 8:54:32 01:36 8:54:56 01:47 8:58:36 01:36 9:17:25 01:12 9:58:00 03:22 10:30:12 01:39 11:03:25 02:16 11:39:40 01:38 11:53:15 02:50 11:55:48 02:01 12:08:21 01:39 12:14:21 02:03 12:28:56 02:45 12:53:51 02:26 |
#2
Posted to microsoft.public.excel.misc
|
|||
|
|||
Graph standardized values
1. Use XY charts
2. In each chart, double click the X axis, and on the Scale tab, enter 8:00 for min, 13:00 for max, and 1:00 or 0:30 for major unit. Hint: Do one chart's X axis, select the next chart's X axis and press F4 to repeat, and do this for each subsequent chart. 3. In each chart, double click the Y axis, and on the Scale tab, enter 0 for min, 0:05 for max, and 0:01 or 0:0:30 for major unit. Hint: Do one chart's Y axis, select the next chart's Y axis and press F4 to repeat, and do this for each subsequent chart. - Jon ------- Jon Peltier, Microsoft Excel MVP Tutorials and Custom Solutions http://PeltierTech.com _______ "Arianit Dobroshi" wrote in message ups.com... I need to standardize a multitude of graphs so they can be compared. The time in minutes (Length) along the vertical axis and the time of day (Oper. Starts) along the horizontal axis should be constant/same for all graphs and the values plotted against those set numbers. In this case data points are from 8:00 to 13:00 and values are from 0 to 5 minutes. Is it possible to have all the tables for different days of equal length? How? Oper. Starts Length 8:09:20 02:10 8:50:30 01:47 8:54:32 01:36 8:54:56 01:47 8:58:36 01:36 9:17:25 01:12 9:58:00 03:22 10:30:12 01:39 11:03:25 02:16 11:39:40 01:38 11:53:15 02:50 11:55:48 02:01 12:08:21 01:39 12:14:21 02:03 12:28:56 02:45 12:53:51 02:26 |
#3
Posted to microsoft.public.excel.misc
|
|||
|
|||
Graph standardized values
Works like a charm.
Thanks, Ari On Mar 22, 4:44 am, "Jon Peltier" wrote: 1. Use XY charts 2. In each chart, double click the X axis, and on the Scale tab, enter 8:00 for min, 13:00 for max, and 1:00 or 0:30 for major unit. Hint: Do one chart's X axis, select the next chart's X axis and press F4 to repeat, and do this for each subsequent chart. 3. In each chart, double click the Y axis, and on the Scale tab, enter 0 for min, 0:05 for max, and 0:01 or 0:0:30 for major unit. Hint: Do one chart's Y axis, select the next chart's Y axis and press F4 to repeat, and do this for each subsequent chart. - Jon ------- Jon Peltier, Microsoft Excel MVP Tutorials and Custom Solutionshttp://PeltierTech.com _______ "Arianit Dobroshi" wrote in message ups.com... I need to standardize a multitude of graphs so they can be compared. The time in minutes (Length) along the vertical axis and the time of day (Oper. Starts) along the horizontal axis should be constant/same for all graphs and the values plotted against those set numbers. In this case data points are from 8:00 to 13:00 and values are from 0 to 5 minutes. Is it possible to have all the tables for different days of equal length? How? Oper. Starts Length 8:09:20 02:10 8:50:30 01:47 8:54:32 01:36 8:54:56 01:47 8:58:36 01:36 9:17:25 01:12 9:58:00 03:22 10:30:12 01:39 11:03:25 02:16 11:39:40 01:38 11:53:15 02:50 11:55:48 02:01 12:08:21 01:39 12:14:21 02:03 12:28:56 02:45 12:53:51 02:26 |
#4
Posted to microsoft.public.excel.misc
|
|||
|
|||
Graph standardized values
I should note that in Excel 2007, the ability to enter XY chart axis
parameters in date and time format is not working. This bug has been reported and they're considering it for a future fix. - Jon ------- Jon Peltier, Microsoft Excel MVP Tutorials and Custom Solutions http://PeltierTech.com _______ "Jon Peltier" wrote in message ... 1. Use XY charts 2. In each chart, double click the X axis, and on the Scale tab, enter 8:00 for min, 13:00 for max, and 1:00 or 0:30 for major unit. Hint: Do one chart's X axis, select the next chart's X axis and press F4 to repeat, and do this for each subsequent chart. 3. In each chart, double click the Y axis, and on the Scale tab, enter 0 for min, 0:05 for max, and 0:01 or 0:0:30 for major unit. Hint: Do one chart's Y axis, select the next chart's Y axis and press F4 to repeat, and do this for each subsequent chart. - Jon ------- Jon Peltier, Microsoft Excel MVP Tutorials and Custom Solutions http://PeltierTech.com _______ "Arianit Dobroshi" wrote in message ups.com... I need to standardize a multitude of graphs so they can be compared. The time in minutes (Length) along the vertical axis and the time of day (Oper. Starts) along the horizontal axis should be constant/same for all graphs and the values plotted against those set numbers. In this case data points are from 8:00 to 13:00 and values are from 0 to 5 minutes. Is it possible to have all the tables for different days of equal length? How? Oper. Starts Length 8:09:20 02:10 8:50:30 01:47 8:54:32 01:36 8:54:56 01:47 8:58:36 01:36 9:17:25 01:12 9:58:00 03:22 10:30:12 01:39 11:03:25 02:16 11:39:40 01:38 11:53:15 02:50 11:55:48 02:01 12:08:21 01:39 12:14:21 02:03 12:28:56 02:45 12:53:51 02:26 |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Help with charting my own y values on a graph | Excel Discussion (Misc queries) | |||
Values for Graph | Excel Discussion (Misc queries) | |||
Unwanted zero values in a graph | Excel Discussion (Misc queries) | |||
do not graph zero calculated values. | Charts and Charting in Excel | |||
how do i link data from multiple standardized excel files | Excel Discussion (Misc queries) |