In this case, I want to use VBA only. No Scheduling tools.

My field of application is Construction where you repeatedly compare
Schedule of Estimated Data, Actual Data and Final Forecast.

The following data would drive a floating cluster of 3 bars,
Estimated, Actual and Forecast Finish from the current Report Date.

Activity# | Estimated Start | Estimated Finish | Actual Start
| Actual Finish | Forecast Finish | % Complete

Dim's .....
Set Series = .......
Set ReportDate = ....
For I = 1 to Ser.Points.Count
Draw Estimated bar from Estimated Start to Estimated Finish [Blue
1/4" or 6mmThick]
If Point# is 100% Complete
Draw Actual Bar from Actual Start to Actual Finish [Red
3/16" or 5mm Thick]
Else
Draw Actual Bar from Actual Start to Current Reporting
Date [Red 3/16" or 5mm Thick]
Draw Final Forecast Bar from Current Reporting Date to
Final Forecast [Yellow 3/16" or 5mm Thick]
End If
Next I
Draw Reporting Date Vertical marker


Thank you for your help or clues on these floating clusters

Have a good day,

J.P.

  #2   Report Post  
Posted to microsoft.public.excel.charting
external usenet poster
 
Posts: 6,582
Default How do I draw a floating cluster Gantt Chart with VBA.

You don't need VBA, just charts:

http://pubs.logicalexpressions.com/P...cle.asp?ID=343
(temporarily down, but should be up by next week)
http://peltiertech.com/Excel/Charts/GanttChart.html

- Jon
-------
Jon Peltier, Microsoft Excel MVP
Tutorials and Custom Solutions
http://PeltierTech.com
_______


"u473" wrote in message
ups.com...
In this case, I want to use VBA only. No Scheduling tools.

My field of application is Construction where you repeatedly compare
Schedule of Estimated Data, Actual Data and Final Forecast.

The following data would drive a floating cluster of 3 bars,
Estimated, Actual and Forecast Finish from the current Report Date.

Activity# | Estimated Start | Estimated Finish | Actual Start
| Actual Finish | Forecast Finish | % Complete

Dim's .....
Set Series = .......
Set ReportDate = ....
For I = 1 to Ser.Points.Count
Draw Estimated bar from Estimated Start to Estimated Finish [Blue
1/4" or 6mmThick]
If Point# is 100% Complete
Draw Actual Bar from Actual Start to Actual Finish [Red
3/16" or 5mm Thick]
Else
Draw Actual Bar from Actual Start to Current Reporting
Date [Red 3/16" or 5mm Thick]
Draw Final Forecast Bar from Current Reporting Date to
Final Forecast [Yellow 3/16" or 5mm Thick]
End If
Next I
Draw Reporting Date Vertical marker


Thank you for your help or clues on these floating clusters

Have a good day,

J.P.



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
More than one value on a cluster colum chart Haylie Charts and Charting in Excel 1 November 28th 06 04:05 AM
Stack & Cluster columns in same chart Chris Charts and Charting in Excel 2 October 24th 06 11:07 PM
cluster & stacked & line in one chart Scott Charts and Charting in Excel 3 April 11th 06 05:26 PM
Widening Cluster Chart Columns toilinthedark Charts and Charting in Excel 2 October 31st 05 08:36 PM
how do I create a cluster chart? JoanH Charts and Charting in Excel 2 April 16th 05 06:58 PM


All times are GMT +1. The time now is 11:21 PM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"