Calculate parts per hour on rotating line
so, one part per foot, moving at 7.5 feet per minute, that means you are
getting 7.5 parts per minute, divide 500 parts by 7.5 parts per minute gives
you 66.6666666666666666 minutes to get 500 parts
"scootr" wrote:
There is a 700 feet rotating conveyor.
Moving at a rate of 7.5 feet per minute.
I know it takes 93 minutes to make one revolution.
How long will it take to get 500 parts off the line?
The parts are spaced 1 foot apart.
I need a formula that can calculate this. Can somebody help me?
|