Try

=(stacking_achieved+cleaning_achieved)/((stacking_hours*stacking_target_per_hour)+(cleani ng_hours*cleaning_target_per_hour))

--

HTH

Bob

"Azza1986" wrote in message
...
I want to work out the total percentage of 2 sums,
For example
Matthew worked 5 hours stacking shelfs, in this time he stacked 40
shelves,
his target was to stack 10 shelves per hour so his current percentage
would
be 80%.
Matthew then works 3 hours cleaning shelves, in this time he cleaned 45
shelves, his target was to clean 15 shelves per hour so on this job he is
hitting 100%.

What I need to know is what formula I need to use to calculate his overall
percentage for the day, taking into account the duration he spent on each
job????