Dates formula
Hi,
You need the workday formula. With your start date June 1 2009 in a1 try this
=WORKDAY(A1,5,Holidays)
Holidays is a named range that contain holiday dates. You can then reference
the cell with this formula in in the same way to get your next milestone.
Mike
"Kristina1976" wrote:
I need some assistance in creating a formula for dates. What I am trying to
do is create a project time line based on workdays Mon - Fri plus exclude
holidays
I have a start date and a completion date however I need to have specific
tasks completed throughout the project. ie
Start date June 1, 2009
Design June 1st plus 5 days
(this is where I need the formula, again taking into consideration this needs
to be Mon-Fri, & not a holiday)
Print June 5 plus 2 days
(this is where I need the formula, again taking into consideration this needs
to be Mon-Fri, & not a holiday)
End date June 30th, 2009
Any help is greatly appreciated
|