The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes, what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right information
in
the correct fields. The schedule is set up to have A1 to be the start date
and B1 the finish date. We have multiple units being built at once. They
take
10 days to complete, with a 4-day workweek. If you could walk me through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not
count
Friday (Sat or Sun) in the duration of the projects. I just need a
correct
end date for the projects.

Thanks so much!!!