Jomo Watts wrote:
I have a Timesheet that has a row of dates for a two week period, I
would
like to enter the first date and have the rest of the remaining days
auto
compute the correct date. I used to have a Timesheet that had a
formula for
this but I'am no longer able to find it.
Thanks
If your date appears in cell A1, for instance, then cell A2 could
contain the formula =A1+1; cell A3 could contain =A2+1..... Just copy
down as many rows to complete your two week period.
|