How can I count the working day
Try this out, worked for my little test
=WORKDAY(B1,0)-WORKDAY(A1,0)
--
-John
Please rate when your question is answered to help us and others know what
is helpful.
"onur" wrote:
How can I count the working day between two date,exlude saturday sunday and
30.08.2007.
The notice is there may be too many dates in two date coloumn and at some
rows 2nd. dates may not pass 30.08.2007
help me
thank you
|