Project Management - Start & End Date Calculations
I am setting up a combination project management and financial spreadsheet
for a builder. I want to calculate the ending date from the duration days.
If I put in Monday, 6/12/06 and add three days, the result is Thursday,
6/15/06. this is as if it is adding 3 days from the end of Monday vs 8am
Monday. (Not the way the builder thinks.)
Is there a setting I'm missing that will return the date Wednesday, 6/14?
Also, the builder is still on MSOffice 2002 so NETWORKDAYS function is not
available to him. Naturally, he wants no beginning or end dates to fall on
weekends. Anyone have a formula to accomodate that?
|