Default workdays formula ends on weekend date

Hi!

I don't know why you're subtracting a day, but you need to subtract the day
inside the function:

=WORKDAY("1/3/2006",29-1)

But if you're doing that then why not just:

=WORKDAY("1/3/2006",28)

Biff

"Charles C." <Charles wrote in message
...
I'm trying to calculate end dates similar to MS Project based upon a start
date and duration in workdays.

Start Date = 1/3/2006
Workdays = 28 - 1 day adjustment to get the END DATE
Holidays = ignore for now, not using it

Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
this is okay, but when increased to 29 days the end date should be
2/10/2006
but Excel jumps to 2/12/2006 which is a Sunday.