I'm trying to calculate end dates similar to MS Project based upon a start
date and duration in workdays.

Start Date = 1/3/2006
Workdays = 28 - 1 day adjustment to get the END DATE
Holidays = ignore for now, not using it

Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
this is okay, but when increased to 29 days the end date should be 2/10/2006
but Excel jumps to 2/12/2006 which is a Sunday.

Why? What am i doing wrong?

  #2   Report Post  
Posted to microsoft.public.excel.worksheet.functions
Biff
 
Posts: n/a
Default workdays formula ends on weekend date

Hi!

I don't know why you're subtracting a day, but you need to subtract the day
inside the function:

=WORKDAY("1/3/2006",29-1)

But if you're doing that then why not just:

=WORKDAY("1/3/2006",28)

Biff

"Charles C." <Charles wrote in message
...
I'm trying to calculate end dates similar to MS Project based upon a start
date and duration in workdays.

Start Date = 1/3/2006
Workdays = 28 - 1 day adjustment to get the END DATE
Holidays = ignore for now, not using it

Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
this is okay, but when increased to 29 days the end date should be
2/10/2006
but Excel jumps to 2/12/2006 which is a Sunday.

Why? What am i doing wrong?



  #3   Report Post  
Posted to microsoft.public.excel.worksheet.functions
Charles C.
 
Posts: n/a
Default workdays formula ends on weekend date

Biff

Subtracting the day becuase workdays is inclusive of the start and end dates.

Doing it outside of the formula was the problem.
Thanks.

"Biff" wrote:

Hi!

I don't know why you're subtracting a day, but you need to subtract the day
inside the function:

=WORKDAY("1/3/2006",29-1)

But if you're doing that then why not just:

=WORKDAY("1/3/2006",28)

Biff

"Charles C." <Charles wrote in message
...
I'm trying to calculate end dates similar to MS Project based upon a start
date and duration in workdays.

Start Date = 1/3/2006
Workdays = 28 - 1 day adjustment to get the END DATE
Holidays = ignore for now, not using it

Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
this is okay, but when increased to 29 days the end date should be
2/10/2006
but Excel jumps to 2/12/2006 which is a Sunday.

Why? What am i doing wrong?




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Trending Formula Results by Date sony654 Excel Worksheet Functions 0 January 2nd 06 02:33 AM
Match then lookup Tenacity Excel Worksheet Functions 9 December 3rd 05 05:30 AM
NETWORKDAYS - Multiple Date Selection Annabelle Excel Discussion (Misc queries) 3 October 4th 05 07:04 PM
Formula checking multiple worksheets sonic-the-mouse Excel Worksheet Functions 2 June 5th 05 07:48 PM
Formula checking multiple worksheets sonic-the-mouse Excel Worksheet Functions 2 June 5th 05 03:28 AM


All times are GMT +1. The time now is 10:50 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"