View Single Post
  #3   Report Post  
gibbylinks
 
Posts: n/a
Default

Thanks for quick reply, but it's not that straight forward..... the value in
B2 at present is just a number i.e 2.3 meaning 2.3 hours in duration.

Any tips ?

"Bob Phillips" wrote:

Assuming that the start time is in A2, job time in B2, and they are both
formatted as time, just use

=ROUND((A2+B2)*96,0)/96

--

HTH

RP
(remove nothere from the email address if mailing direct)


"gibbylinks" wrote in message
...
I have two columns. One which calculates the length of time a job will

take
to run on a machine, and the other in which we put the time the job will

come
off the machine. At present we enter the time off manually. Is it possible

to
calculate the time off automatically (to the nearest 1/4 of an hour) if we
put in a start time ?

Thanks