Hi, DL
1)On the train home from Boston, I was thinking that my original formula
could stand some improvements. You took care of that nicely.
2)Regarding:
doesn't look like there was a need to consider start date on a holiday<<
I allowed that the start date might be logged by a help desk that's takes
calls 24/7 but the SLA only includes standard workdays. Whether that's true
or not, the new formula calculates the right target date.
***********
Best Regards,
Ron
XL2002, WinXP-Pro
"daddylonglegs" wrote:
Ron Coderre Wrote:
=WORKDAY(A1,4+OR(WEEKDAY(A1,2)5,ISNUMBER(MATCH(A1 ,$J$1:$J$10,0))),$J$1:$J$10)
Hi Ron,
doesn't look like there was a need to consider start date on a holiday
but if there was you could use
=WORKDAY(WORKDAY(A1,-1,J$1:J$10),5,J$1:J$10)
--
daddylonglegs
------------------------------------------------------------------------