Business Days Including Holidays
Hmm...Maybe I was not clear...What I need to do is this...lets say I know the
start time, (Monday July 3rd 2006 the 4th is a holiday) I know that this
grouo has 5 business days to be completed. I need to then have excel give me
the date of the 5th business day excluding the holiday (Juky 4th).
Thanx again
" wrote:
surely you don't need to find the next business day - if you know when
the task started and when it finished, NetWorkDays will deduct the
weekends and holidays to give you the elapsed time - which you can then
use to determine if within 1 business day or 5 business days etc
I remember a good few years ago now building a very complicated formula
to calculate service time which not only had to cater for days, but
allow for a task being logged outside working hours and finished
outside working hours - it had to bring the relevent date back or
forwards as appropriate to ONLY count chargeable elapsed time!
|