Fixed Duration-strange calculation
I've inserted a new task that I wanted to have a duration of 3 week. I
changed the duration to fixed (which removed the ?) for 3w. The default start date of the project is 1/3...the calculated end date ended up being 1/12...no where near 3 weeks. I have tried every task type FD,FU,FW with effort driven box both checked and uchecked. I've tried assigning various values for estimated work. I have tried setting the duration to 15d. I just can't make it work. Help! -- TraceyH |