Ok, if I want to date successive column headings to return progressive dates,
I can use Today (), Today() + 1, Today + 2, etc. What if I want this progression to skip weekend and holiday dates? |
#2
![]() |
|||
|
|||
![]()
Put a Monday date in your first column.
Right click and drag the fill handle aross as many columns as you estimate you'll need. When you release the mouse, you'll see a pop-up menu with one of the choices to fill the range with "weekdays". As for holidays, only you know what's a holiday for your firm (Veteran's Day - Friday after Thanksgiving). You'll have to adjust for them manually. -- HTH, RD ============================================== Please keep all correspondence within the Group, so all may benefit! ============================================== "Shadyhosta" wrote in message ... Ok, if I want to date successive column headings to return progressive dates, I can use Today (), Today() + 1, Today + 2, etc. What if I want this progression to skip weekend and holiday dates? |
#3
![]() |
|||
|
|||
![]() "Shadyhosta" wrote: Ok, if I want to date successive column headings to return progressive dates, I can use Today (), Today() + 1, Today + 2, etc. What if I want this progression to skip weekend and holiday dates? |
#4
![]() |
|||
|
|||
![]()
I don't understand why a "Monday" date. I want my first column to be
today() + 1. I tried this formula, and then tried right clicking on the cell, but only got a drop down menu, and was unable to drag. "RagDyer" wrote: Put a Monday date in your first column. Right click and drag the fill handle aross as many columns as you estimate you'll need. When you release the mouse, you'll see a pop-up menu with one of the choices to fill the range with "weekdays". As for holidays, only you know what's a holiday for your firm (Veteran's Day - Friday after Thanksgiving). You'll have to adjust for them manually. -- HTH, RD ============================================== Please keep all correspondence within the Group, so all may benefit! ============================================== "Shadyhosta" wrote in message ... Ok, if I want to date successive column headings to return progressive dates, I can use Today (), Today() + 1, Today + 2, etc. What if I want this progression to skip weekend and holiday dates? |
#5
![]() |
|||
|
|||
![]()
You need to refer to the previous cell if you want to add 1 to each day (or
using the COLUMN function) put TODAY() (or press ctrl + ;) in A1, in B1 put this formula and copy across =IF(A1="","",IF(WEEKDAY(A1+1,2)5,A1+7-WEEKDAY(A1-2),A1+1)) will skip weekends but you obviously have to fix the holidays manually or put them in a list and add some conditions if the dates match dates in the list -- Regards, Peo Sjoblom (No private emails please, for everyone's benefit keep the discussion in the newsgroup/forum) "Shadyhosta" wrote in message ... I don't understand why a "Monday" date. I want my first column to be today() + 1. I tried this formula, and then tried right clicking on the cell, but only got a drop down menu, and was unable to drag. "RagDyer" wrote: Put a Monday date in your first column. Right click and drag the fill handle aross as many columns as you estimate you'll need. When you release the mouse, you'll see a pop-up menu with one of the choices to fill the range with "weekdays". As for holidays, only you know what's a holiday for your firm (Veteran's Day - Friday after Thanksgiving). You'll have to adjust for them manually. -- HTH, RD ============================================== Please keep all correspondence within the Group, so all may benefit! ============================================== "Shadyhosta" wrote in message ... Ok, if I want to date successive column headings to return progressive dates, I can use Today (), Today() + 1, Today + 2, etc. What if I want this progression to skip weekend and holiday dates? |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
how to increase maximum number of columns in excel 2003 | Excel Discussion (Misc queries) | |||
Columns in Excel will not allow user to click in them | Excel Discussion (Misc queries) | |||
Counting the Contents of Two Columns | Excel Discussion (Misc queries) | |||
Averaging columns | New Users to Excel | |||
interchange columns with rows | Excel Discussion (Misc queries) |