  #1   Report Post  
LoveBuildingHouses
 
Posts: n/a
Default Help with a Date Formula

I currently use this formula to create house building schedules:
=AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1))

It only allows me to schedule weekdays; however, it doesnt account for
holidays. I would like to be able to set it up so that it will recognize the
6 remaining days that I consider to be holidays this year. I would like for
it skip to the next available weekday after that holiday. The holidays a
11-24, 11-25, 12-22, 12-23, 12-29, 12-30

Thanks for your help! Trista
  #2   Report Post  
Robbo
 
Posts: n/a
Default

Have you tried using the 'WORKDAY' function? This allows you to enter
holidays into the calculation.

If it isn't available in your function list, go to Tools, Add-Ins, and then
click the analysis toolpak option. This gives you some more functions.

"LoveBuildingHouses" wrote:

I currently use this formula to create house building schedules:
=AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1))

It only allows me to schedule weekdays; however, it doesnt account for
holidays. I would like to be able to set it up so that it will recognize the
6 remaining days that I consider to be holidays this year. I would like for
it skip to the next available weekday after that holiday. The holidays a
11-24, 11-25, 12-22, 12-23, 12-29, 12-30

Thanks for your help! Trista

  #3   Report Post  
LoveBuildingHouses
 
Posts: n/a
Default

Thanks so much for your help! I figured it out and my formula is now ALOT
shorter. Have a great day!

"Robbo" wrote:

Have you tried using the 'WORKDAY' function? This allows you to enter
holidays into the calculation.

If it isn't available in your function list, go to Tools, Add-Ins, and then
click the analysis toolpak option. This gives you some more functions.

"LoveBuildingHouses" wrote:

I currently use this formula to create house building schedules:
=AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1))

It only allows me to schedule weekdays; however, it doesnt account for
holidays. I would like to be able to set it up so that it will recognize the
6 remaining days that I consider to be holidays this year. I would like for
it skip to the next available weekday after that holiday. The holidays a
11-24, 11-25, 12-22, 12-23, 12-29, 12-30

Thanks for your help! Trista

Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Formula checking multiple worksheets sonic-the-mouse Excel Worksheet Functions 2 June 5th 05 03:28 AM
addition to my date formula...required Juco Excel Worksheet Functions 5 January 30th 05 11:48 AM
Excel formula with date constraints Warrior Pope Excel Discussion (Misc queries) 3 January 28th 05 03:08 PM
Formula with date constraints Warrior Pope Excel Worksheet Functions 1 January 28th 05 02:11 PM
Need help troubleshooting an array formula XLXP on Win2K KR Excel Worksheet Functions 1 December 13th 04 07:41 PM


All times are GMT +1. The time now is 11:04 AM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"