I currently use this formula to create house building schedules:
=AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1)) It only allows me to schedule weekdays; however, it doesnt account for holidays. I would like to be able to set it up so that it will recognize the 6 remaining days that I consider to be holidays this year. I would like for it skip to the next available weekday after that holiday. The holidays a 11-24, 11-25, 12-22, 12-23, 12-29, 12-30 Thanks for your help! Trista |
#2
![]() |
|||
|
|||
![]()
Have you tried using the 'WORKDAY' function? This allows you to enter
holidays into the calculation. If it isn't available in your function list, go to Tools, Add-Ins, and then click the analysis toolpak option. This gives you some more functions. "LoveBuildingHouses" wrote: I currently use this formula to create house building schedules: =AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1)) It only allows me to schedule weekdays; however, it doesnt account for holidays. I would like to be able to set it up so that it will recognize the 6 remaining days that I consider to be holidays this year. I would like for it skip to the next available weekday after that holiday. The holidays a 11-24, 11-25, 12-22, 12-23, 12-29, 12-30 Thanks for your help! Trista |
#3
![]() |
|||
|
|||
![]()
Thanks so much for your help! I figured it out and my formula is now ALOT
shorter. Have a great day! "Robbo" wrote: Have you tried using the 'WORKDAY' function? This allows you to enter holidays into the calculation. If it isn't available in your function list, go to Tools, Add-Ins, and then click the analysis toolpak option. This gives you some more functions. "LoveBuildingHouses" wrote: I currently use this formula to create house building schedules: =AD127+IF(WEEKDAY(AD127)=7,2,IF(WEEKDAY(AD127)=6, 3,1)) It only allows me to schedule weekdays; however, it doesnt account for holidays. I would like to be able to set it up so that it will recognize the 6 remaining days that I consider to be holidays this year. I would like for it skip to the next available weekday after that holiday. The holidays a 11-24, 11-25, 12-22, 12-23, 12-29, 12-30 Thanks for your help! Trista |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Formula checking multiple worksheets | Excel Worksheet Functions | |||
addition to my date formula...required | Excel Worksheet Functions | |||
Excel formula with date constraints | Excel Discussion (Misc queries) | |||
Formula with date constraints | Excel Worksheet Functions | |||
Need help troubleshooting an array formula XLXP on Win2K | Excel Worksheet Functions |