I am not sure if this can be done but here is what I am looking for help with
I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |
#2
|
|||
|
|||
Hi
Have a look at NETWORKDAYS function - as this only uses working days. I think it's part of the Analysis Toolpak add-in. -- Andy. "Kim CB" wrote in message ... I am not sure if this can be done but here is what I am looking for help with I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |
#3
|
|||
|
|||
Are your business hours 24 hours a day? If not, if it goes down at say 3PM
one day and is back 11AM the next, how many hours are lost. In other words, what is the start and end times? -- HTH Bob Phillips "Kim CB" wrote in message ... I am not sure if this can be done but here is what I am looking for help with I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |
#4
|
|||
|
|||
No I am looking at an 8 hour business Day. So what happens is I get a dump
of raw data that give me a date and time that a machine goes down as well as the date and time the machine is back up. Ex. Printer ABC Down 1/21/05 8:27AM Printer ABC Up 2/03/05/ 3:25pm Based on these 2 columns I need something that says - the machine was down for X number of bus days ( based on an 8hr bus day and subtracting any weekend that fell in there) -- Kim "Bob Phillips" wrote: Are your business hours 24 hours a day? If not, if it goes down at say 3PM one day and is back 11AM the next, how many hours are lost. In other words, what is the start and end times? -- HTH Bob Phillips "Kim CB" wrote in message ... I am not sure if this can be done but here is what I am looking for help with I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |
#5
|
|||
|
|||
Thanks Andy I will do that!
-- Kim "Andy B" wrote: Hi Have a look at NETWORKDAYS function - as this only uses working days. I think it's part of the Analysis Toolpak add-in. -- Andy. "Kim CB" wrote in message ... I am not sure if this can be done but here is what I am looking for help with I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |
#6
|
|||
|
|||
So in my example, was that down for 2 days, even though it was probably only
5 working hours? -- HTH Bob Phillips "Kim CB" wrote in message ... No I am looking at an 8 hour business Day. So what happens is I get a dump of raw data that give me a date and time that a machine goes down as well as the date and time the machine is back up. Ex. Printer ABC Down 1/21/05 8:27AM Printer ABC Up 2/03/05/ 3:25pm Based on these 2 columns I need something that says - the machine was down for X number of bus days ( based on an 8hr bus day and subtracting any weekend that fell in there) -- Kim "Bob Phillips" wrote: Are your business hours 24 hours a day? If not, if it goes down at say 3PM one day and is back 11AM the next, how many hours are lost. In other words, what is the start and end times? -- HTH Bob Phillips "Kim CB" wrote in message ... I am not sure if this can be done but here is what I am looking for help with I have 2 columns in a spreadsheet that I use to record the date and time that a machine breaks and the date and time that is repaired. Right now the cell formating is mm/dd/yy hh:mm AM/PM - I added a column that calculates how may minuts/hours/days the machine was down. I was wondering if I could change the cell formating that shows not only mm/dd/yy hh:mm AM/PM but also shows the Day of the Week (Mon, Tues, Wed). What I am trying to do is be able to deduct weekend hours from my two columns - So if my machine goes down on Thursday and is back working on Tuesday, I can calculate only how many business hours it was down Any ideas?? Kim |