Posted to microsoft.public.excel.worksheet.functions
|
|||
|
|||
![]()
I am having trouble figuring out how to calculate an end date, give the fact
that a work crew can work 4, 5, 6, or 7 days a week and the activity will take X working days. Here's a simple setup: A1 - Start Date (Provided by Crew) A2 - Work Schedule (4,5,6 or 7 days a week) A3 - Duration of Activity (in working days - 10 for example) A4 - End Date (what I want to calculate) All workdays start on Monday. So if an activity sarts on 9/28/09 and is 10 days long and the crew is working 4/10's (4 days a week, 10 hours a day), then the calculated end date should be 10/13/09 because 10/02 - 10/04 is non-work and 10/09 to 10/11 is also non-work. Any help would be great! -- Thanks in advance! **John** |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
workweek | Excel Discussion (Misc queries) | |||
WorkWeek | Excel Discussion (Misc queries) | |||
Calculating three working days before a date | Excel Worksheet Functions | |||
Calculating recurring date in following month, calculating # days in that period | Excel Worksheet Functions | |||
4 Day Workweek | Excel Worksheet Functions |