Shelly

4 day work week
 

What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not count
Friday (Sat or Sun) in the duration of the projects. I just need a correct
end date for the projects.

Thanks so much!!!


Bob Phillips

4 day work week
 
use this to calculate the working days

=SUMPRODUCT(INT((MAX(end_date,start_date)-WEEKDAY(MAX(end_date,start_date)+1-{2;3;4;5})-MIN(end_date,start_date)+8)/7))

or this if you want to exclude holidays

=SUMPRODUCT(INT((MAX(end_date,start_date)-WEEKDAY(MAX(end_date,start_date)+1-{2;3;4;5})-MIN(end_date,start_date)+8)/7))
-SUMPRODUCT(ISNUMBER(MATCH(WEEKDAY(holidays),{2;3;4 ;5},0))*(holidays=MIN(end_date,start_date))*(holi days<=MAX(end_date,start_date)))

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...

What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not count
Friday (Sat or Sun) in the duration of the projects. I just need a correct
end date for the projects.

Thanks so much!!!




Teethless mama

4 day work week
 
A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not count
Friday (Sat or Sun) in the duration of the projects. I just need a correct
end date for the projects.

Thanks so much!!!


Shelly

4 day work week
 
I'm very new at this program so please bear with me...I did type the formula
in and it didn't work. I think I am just not putting the right information in
the correct fields. The schedule is set up to have A1 to be the start date
and B1 the finish date. We have multiple units being built at once. They take
10 days to complete, with a 4-day workweek. If you could walk me through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not count
Friday (Sat or Sun) in the duration of the projects. I just need a correct
end date for the projects.

Thanks so much!!!


Bob Phillips

4 day work week
 
If you know the start date, and the end date and how long it takes, what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right information
in
the correct fields. The schedule is set up to have A1 to be the start date
and B1 the finish date. We have multiple units being built at once. They
take
10 days to complete, with a 4-day workweek. If you could walk me through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not
count
Friday (Sat or Sun) in the duration of the projects. I just need a
correct
end date for the projects.

Thanks so much!!!




Shelly

4 day work week
 
The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes, what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right information
in
the correct fields. The schedule is set up to have A1 to be the start date
and B1 the finish date. We have multiple units being built at once. They
take
10 days to complete, with a 4-day workweek. If you could walk me through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not
count
Friday (Sat or Sun) in the duration of the projects. I just need a
correct
end date for the projects.

Thanks so much!!!





Bob Phillips

4 day work week
 
=start_date+SIGN(days)*SMALL(IF((WEEKDAY(start_dat e+SIGN(days)*(ROW(INDIRECT("1:"&ABS(days)*10))))={ 1,2,3,4}),ROW(INDIRECT("1:"&ABS(days)*10))),ABS(da ys))

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes, what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right
information
in
the correct fields. The schedule is set up to have A1 to be the start
date
and B1 the finish date. We have multiple units being built at once.
They
take
10 days to complete, with a 4-day workweek. If you could walk me
through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not
count
Friday (Sat or Sun) in the duration of the projects. I just need a
correct
end date for the projects.

Thanks so much!!!







Shelly

4 day work week
 
Where do I put this information?

"Bob Phillips" wrote:

=start_date+SIGN(days)*SMALL(IF((WEEKDAY(start_dat e+SIGN(days)*(ROW(INDIRECT("1:"&ABS(days)*10))))={ 1,2,3,4}),ROW(INDIRECT("1:"&ABS(days)*10))),ABS(da ys))

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes, what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right
information
in
the correct fields. The schedule is set up to have A1 to be the start
date
and B1 the finish date. We have multiple units being built at once.
They
take
10 days to complete, with a 4-day workweek. If you could walk me
through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date and a
duration of days. We work a 4 day work week here and I need to not
count
Friday (Sat or Sun) in the duration of the projects. I just need a
correct
end date for the projects.

Thanks so much!!!








Bob Phillips

4 day work week
 
Anywhere. You just change the variable names to the appropriate cells.

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
Where do I put this information?

"Bob Phillips" wrote:

=start_date+SIGN(days)*SMALL(IF((WEEKDAY(start_dat e+SIGN(days)*(ROW(INDIRECT("1:"&ABS(days)*10))))={ 1,2,3,4}),ROW(INDIRECT("1:"&ABS(days)*10))),ABS(da ys))

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes,
what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right
information
in
the correct fields. The schedule is set up to have A1 to be the
start
date
and B1 the finish date. We have multiple units being built at once.
They
take
10 days to complete, with a 4-day workweek. If you could walk me
through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date
and a
duration of days. We work a 4 day work week here and I need to
not
count
Friday (Sat or Sun) in the duration of the projects. I just need
a
correct
end date for the projects.

Thanks so much!!!










Shelly

4 day work week
 

Thank you for your time Bob!


"Bob Phillips" wrote:

Anywhere. You just change the variable names to the appropriate cells.

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my addy)



"Shelly" wrote in message
...
Where do I put this information?

"Bob Phillips" wrote:

=start_date+SIGN(days)*SMALL(IF((WEEKDAY(start_dat e+SIGN(days)*(ROW(INDIRECT("1:"&ABS(days)*10))))={ 1,2,3,4}),ROW(INDIRECT("1:"&ABS(days)*10))),ABS(da ys))

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
The end date is what I am trying to get...using a 4 day workweek.

"Bob Phillips" wrote:

If you know the start date, and the end date and how long it takes,
what
exactly are you trying to calculate?

--
---
HTH

Bob


(there's no email, no snail mail, but somewhere should be gmail in my
addy)



"Shelly" wrote in message
...
I'm very new at this program so please bear with me...I did type the
formula
in and it didn't work. I think I am just not putting the right
information
in
the correct fields. The schedule is set up to have A1 to be the
start
date
and B1 the finish date. We have multiple units being built at once.
They
take
10 days to complete, with a 4-day workweek. If you could walk me
through
it...that would be so great! And thank you for responding!


"Teethless mama" wrote:

A1: start date
A2: end date

=SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&A2)),2)<5))


"Shelly" wrote:


What I need to do is have a project start date and an end date
and a
duration of days. We work a 4 day work week here and I need to
not
count
Friday (Sat or Sun) in the duration of the projects. I just need
a
correct
end date for the projects.

Thanks so much!!!












All times are GMT +1. The time now is 10:44 AM.

Powered by vBulletin® Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
ExcelBanter.com