Use three cells:
In cell B, enter the hard coded date In cell C, the PM enters an override data if desired In cell A enter: =IF(C1="",B1,C1) So if there is no override, B is displayed. -- Gary''s Student - gsnu200768 "Leslie" wrote: I'm working on a Project Summary workbook, containing a "Dashboard" sheet (which displays a snapshot of the most recent project data), and 4 other sheets: Project Scope, Project Status, Project Change and Project Closure. The Project Manager wants to enter the "Approved Finish Date" into cell A on the Dashboard page at the start of the project, but if this date changes, the PM will enter the changed Approved Finish Date into cell B on the Project Change sheet. I need your help to write a formula that allows the PM to hard key a date into cell A, and still allows cell A to pull data from cell B to replace the hard keyed data in cell A. Is this function possible? If yes, please help me with the formula. |