Thank you both. The number of batches will vary per product and can be
entered in the raw schedule listed below. However they're grouped in 3's.
Meaning that an 8 batch run would be broken as 3, 3, and 2. The formula
calculates how long it would take to run 3 batches, 3 batches (same as
previous 3) and 2 batches. Then, it will add run time in minutes to Start
Time and come up with Finish Time.

The formula for Start and Finish times are in the Raw schedule and uses
information from another sheet in the same workbook.

This is a batching system where first stage production takes place in single
batches and packaging happens in lots of 3s.

If more info is needed, I can provide you a copy of both Raw and detailed
schedules.

Appreciate all the help.

"JLGWhiz" wrote:

Hey Barb, I don't see the formulas either. Hard to copy something that is
not there. Or does one of the cells in one of the columns contain formulas
to copy down? There is a lot of unexplained stuff here.

"Barb Reinhardt" wrote:

Your question doesn't provide all the information necessary to do what you
want.

1) How do you know how many batches of a product are to be run? I'm
thinking that you have 3 lots that are run together, but it's not clear from
the posting.
2) How long is a run for each product?
3) Why do you need to split information every three runs? (3 lots per run?)

Thanks,
Barb Reinhardt



"Mike" wrote:

Hello all,

I have the following data and would like to expand it:
Product Description Line Batches Start Finish

A AAA L1 7 7:00

I like the macro to blow this information into the following schedule:

A AAA L1 3 7:00 8:30
A AAA L1 3 8:00 10:30
A AAA L1 1 10:00 12:00
Changeover 12:00 12:20
B BBB L1 3 12:20 14:20

AND SO ON .....

The macro needs to be smart enough to split the number of batches into 3's
and copy the formulas down, inserts a changeover after each product and go
grab the next product until the last product on the schedule.

Any help would be greatly apprecited.

Mike




 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Do Loops Mike Excel Programming 0 August 29th 08 06:43 PM
Loops alecbowman[_2_] Excel Programming 4 June 11th 06 09:26 AM
Do loops within Do loops Linking to specific cells in pivot table Excel Programming 4 April 14th 05 08:47 AM
Loops PaulSinki Excel Programming 3 December 10th 03 05:01 PM
LOOPS Fernando Duran Excel Programming 2 September 3rd 03 01:07 AM


All times are GMT +1. The time now is 05:52 PM.

Powered by vBulletin® Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2025 ExcelBanter.
The comments are property of their posters.
 

About Us

"It's about Microsoft Excel"