![]() "simsjr" wrote: Hi, I'd like to know if there's a way to make Excel subtract weekend days when calculating actual workdays. For example, I have cells for the start date and end date of a sales forecast. Let's say it's for three weeks (21 days). Now, what I'd like to do is subtract the weekend days (there are 6 in this period) to get the "15". Now, if I was only doing a forecast for three weeks at a time, I could just have Excel subtract the 6 weekend days with a simple subtraction formula. However, we want this report to scale to any time period and subtract any weekend days that occur in that period. Make sense? Is there a way to do this? I have Excel 97 if that means anything. End date minus Start Date = Total days networkday(Start,End) = Workdays Difference is weekend days |
#2
![]()
Posted to microsoft.public.excel.programming
|
|||
|
|||
![]()
Hello,
I suggest to have a look he http://www.sulprobil.com/html/date_formulas.html It reads: Count of working days (Mondays through Fridays without any holidays): A1 Start date A2 End date Formula: =(A2-WEEKDAY(A2,2)+WEEKDAY(A1,2)-A1)/7*5-MIN(5,WEEKDAY(A1,2))+MIN(5, WEEKDAY(A2,2)) This formula is different from Excel's built-in function (analysis add-in). It counts from A1 24:00 until A2 24:00. HTH, Bernd |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
How to subtract weekend days? | Excel Programming | |||
How to subtract weekend days? | Excel Programming | |||
How to subtract weekend days? | Excel Programming | |||
How to subtract weekend days? | Excel Programming | |||
How to subtract weekend days? | Excel Programming |